Page 4 - Shire of Roebourne
Page 4 - Shire of Roebourne
Page 4 - Shire of Roebourne
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Ordinary Council Meeting – Agenda 16 February 2009<br />
Expenditure<br />
Expenditure has a variance <strong>of</strong> down 0.61% ($2,945) which is below the threshold to report.<br />
Other Property and Services<br />
Revenue<br />
Revenue has a variance <strong>of</strong> down 2.26% ($9,044) which is below the threshold to report.<br />
Expenditure<br />
Expenditure has a variance <strong>of</strong> up 4,245.13% ($121,944). The main variances are as follows:<br />
1) $81,303 down on Less costs allocated to Works (timing difference)<br />
2) $95,016 down on superannuation paid (due to timing difference)<br />
3) $192,411 down on Less allocated Plant Operating Costs<br />
4) $13,035 down on PWO Design & Investigation<br />
5) $20,773 down on PWO Superannuation<br />
Capital<br />
Revenue<br />
Capital Revenue shows a variance <strong>of</strong> 0.00% ($1) which is below the threshold to report.<br />
Expenditure<br />
Capital expenditure shows a variance <strong>of</strong> down 8.49% ($473,141). The main variances are due<br />
to timing differences as follows:<br />
1) $305,599 up on purchase <strong>of</strong> land for staff housing $14,007 up on Staff Housing Building<br />
2) $110,000 not yet spent on Redevelopment Karratha Leisure Centre<br />
3) $35,000 not yet spent on 7 Mile Tip Building Improvements<br />
4) $50,000 not yet spent on Karratha Depot Building Improvements<br />
5) $100,000 not yet spent on Karratha Airport Common User Check in Facility<br />
6) $46,820 not yet spent on Computer Equipment<br />
7) $47,665 not yet spent on purchasing Plant<br />
8) Infrastructure as follows:<br />
$30,000 not yet spent on Karratha Golf Course Seeding<br />
$40,625 not yet spent on Toilets Dampier Boat Ramp<br />
$20,833 not yet spent on Point Samson Centenary Projects<br />
$19,312 not yet spent on Dampier Lookout Rehabilitation<br />
$57,204 not yet spent on Footpath – Hill Rd to Warburton Crescent<br />
$25,000 not yet spent on Karratha Airport Low Power Voltage Upgrade<br />
$180,000 not yet spent on Karratha Airport Apron Lighting<br />
RATES<br />
Variance shown is up 1.46% ($182,405) being additional back rates and interim rates.<br />
<strong>Page</strong> 34