DRA GLOBAL<br />
Bel Air Bauxite<br />
220<br />
In 2017 DRA Global was<br />
awarded the contract for the<br />
development of a port facility<br />
and associated infrastructure<br />
for the export of bauxite, by<br />
Alufer Mining in Guinea. The<br />
Alufer Bel Air Mine project was<br />
DRA’s first causeway<br />
development, which expanded<br />
the company’s exposure within<br />
the marine environment. Bel<br />
Air was expected to have an<br />
initial production rate of 5.5<br />
million tonnes per annum and<br />
included a 22.5km haul road<br />
running over eight river<br />
crossings, an export facility<br />
with the ROM tip that feeds a<br />
6500-tonne live capacity<br />
stockpile, and a causeway<br />
extending 1.4km into the<br />
Atlantic Ocean, where a barge<br />
load out berth was constructed.<br />
The scope included all the<br />
necessary infrastructure to<br />
operate the facility:<br />
construction camp, wellfields,<br />
power generation, offices,<br />
laboratory, workshop and<br />
a bailey bridge across the<br />
Koundinde<br />
Work on the project<br />
commenced in January 2017<br />
and was completed in August<br />
2018 before commercial<br />
production was achieved within<br />
the first six months of<br />
operation. Alufer is on target to<br />
reach its annual production<br />
rate of 5.5 million wet tonnes by<br />
the end of <strong>2019</strong>. DRA Global’s<br />
extensive material handling,<br />
earthworks and infrastructure<br />
design capabilities have<br />
contributed significantly to<br />
the success of the project.<br />