6.1.9 On-going projects<br />
City Development Plan for Agra City in the state of Uttar Pradesh under <strong>JNNURM</strong><br />
Currently, water supply<br />
scheme which is under<br />
execution is under Taj<br />
Trapezium Zone (TTZ)<br />
programme. The scheme<br />
aims at reorganizing the<br />
conveyance mains,<br />
balancing reservoirs, and<br />
distribution system for<br />
uniform and effective<br />
distribution of treated water<br />
and extending the water<br />
supply facility in the newly<br />
developed area. The<br />
estimated pre design cost<br />
of this scheme was Rs.<br />
72.80 crore of which Rs.<br />
61.50 crore worth projects<br />
Fig 6.1: Taj Trapezium Zone<br />
are either under progress or completed / commissioned.<br />
TTZ programme was initiated in 1997-98 for protection of Taj Mahal. The funding of this<br />
programme is equally shared by Central and State Government. The initial amount agreed<br />
upon was Rs. 600 crore. Funds were placed at disposal of a state level Mission Management<br />
Board (M.M.B) with Chief Secretary as its Chairman. Further in 1999-2000 a Taj Trapezium<br />
Environment Conservation Fund was constituted to ensure availability of funds for schemes<br />
intended to environmental protection of Taj Mahal and placed at the disposal of M.M.B.<br />
S.<br />
No.<br />
Table: 6.6- Present Status of TTZ Programme<br />
Item Status<br />
before<br />
T.T.Z.<br />
Works<br />
proposed in<br />
T.T.Z.<br />
-35-<br />
MDP Consultants in association with Allianz Securities Ltd<br />
Works completed<br />
in T.T.Z.<br />
Present<br />
status<br />
1 Zonal pumping<br />
station<br />
11 Nos. 10 Nos. 2 Nos. 13 Nos.<br />
2 Rising main 32 Km 32 Km 22 Km 54 Km<br />
3 Distribution net work 418 Km 818 Km 419 Km 837 Km<br />
4 Clear water storage<br />
OHT/CWR<br />
51974 Kl 36325 Kl 2882 Kl 80799 Kl<br />
Source: U.P. Jal Nigam; June 2006<br />
6.1.10 Major Issues<br />
15 per cent of the city area is not by piped water network.<br />
In Sikandra-II, Bodla-II, Shahganj-III, Tajganj-II & III, Trans Yamuna-II & Ghatwasan-II the<br />
water requirement is met by Hand pumps and tankers.<br />
The UFW ranges between 40-45 per cent of the total supply, which is very high.<br />
The pressure at tail end is very low.<br />
Excessive water loss due to leaks in water pipes and pipe appurtenances.<br />
Damaged water mains and distribution mains.<br />
95 per cent of the leakages due to service lines.