6.24 Insurance (For option – <strong>II</strong> & <strong>II</strong>I)<br />

6.24.1 Contractor shall, at his own expense arrange, secure and maintain insurance as may be<br />

necessary with reputable insurance company to the satisfaction of the employer. Bidder’s<br />

failure in this regard shall not relieve him of any of this responsibilities and obligation under<br />

contract. The contractor will insure the goods for its full replacement value till the coated<br />

pipes are handed over to pipeline laying contractor.<br />

6.24.2 Employer will be co – insured in the policy.<br />

6.24.3 Any damage or loss or short receipt noted by the Employer on receipt of material at<br />

warehouse or at the time of taking delivery at warehouse, as the case may be, the employer<br />

might immediately inform the contractor through e- mail / fax / letter .The documentary<br />

evidence shall be forwarded to contractor in due course.<br />

6.24.4 The contractor shall take immediate step to lodge claims with its insurer and arrange to make<br />

good available or immediate replacement of damaged / lost / short receipt material without<br />

waiting for insurance claim settlement.<br />

6.24.5 In case the damage is repairable and carried out by the employer to save time the contractor<br />

will reimburse the cost of repair, immediately on demand.<br />

6.25 Governing Law<br />

Laws of India will govern the contract and Delhi courts will have exclusive jurisdiction on all<br />

matters related to contract.<br />

6.26 Bonus Clause<br />

The bonus clause 27.3 of GCC (procurement of work) is not applicable in the intstant tender.<br />

6.27 Quality Assurance / Quality control<br />

6.27.1 The contractor shall prepare a detailed quality assurance plan for the execution of contract<br />

for various facilities, which will be mutually discussed and agreed to .<br />

6.27.2 The contractor shall establish document and maintain an effective quality assurance system<br />

outlined in recognized codes.<br />

6.27.3 the purchaser / consultant while agreeing to a quality assurance plan shall mark the stages<br />

where they would like to witness the tests; review any or all stages of work at shop / sites as<br />

deemed necessary for quality assurance.<br />

6.28 Performance Evaluation<br />

The performance of contractor to whom the award is placed shall be evaluated right from<br />

submission of bid till the final completion, as per enclosed attachment –I.<br />

<strong>GAIL</strong> (INDIA) LIMITED<br />

New Delhi<br />

Special Conditions of Contract<br />

10 of 10