<strong>Kangaroo</strong> <strong>Island</strong> <strong>Airport</strong> Upgrade <strong>Business</strong> <strong>Case</strong><br />
Source: Tonkin Consulting<br />
Other facilities<br />
Other airside facility works would include:<br />
• Navigational aids and lighting;<br />
• Upgrade of re-fuelling facilities; and<br />
• Detailed design fees.<br />
The introduction of RPT flights from Melbourne and Sydney would likely see a<br />
requirement for refuelling facilities. Consequently, the capital cost of establishing a fuel<br />
storage and dispensing facility have been included in the costing estimates.<br />
6.3 Costing methodology for the options considered<br />
Tonkin Consulting has prepared a report on the engineering investigations that have<br />
been undertaken into the infrastructure requirements and associated estimated capital<br />
costs to upgrade <strong>Kangaroo</strong> <strong>Island</strong> <strong>Airport</strong> based on their understanding of the current<br />
facilities and the condition of those facilities.<br />
The methodology adopted for future development options included:<br />
• undertaking preliminary geometric design work and indicative pavement design for<br />
the required airside extensions;<br />
• determining terminal building spatial requirements at the element level; and<br />
• deriving estimates of capital costs that would deliver the outcomes required for<br />
each option.<br />
A site investigation was undertaken by Tonkin Consulting on 8 th October, 2012 to<br />
assess the underlying structures and civil engineering qualities which would form the<br />
basis of what additional costs were necessary to achieve the required outcomes.<br />
Details of the site and engineering investigation and associated capital costs to an<br />
upgrade are attached in Appendix B.<br />
May 2013<br />
44