<strong>Kangaroo</strong> <strong>Island</strong> <strong>Airport</strong> Upgrade <strong>Business</strong> <strong>Case</strong><br />

allowances for construction on the <strong>Island</strong>. The below table provides a breakdown of<br />

the costs and demonstrates that the major cost items are pavement upgrade and<br />

terminal upgrade. A contingency of 12.5% has also been included as part of the<br />

calculation. Whilst a contingency is included, and highly appropriate for this exercise,<br />

the cost estimates have been prepared after site inspection, and onsite engineering<br />

assessments of the drainage culverts running under the runway. Therefore the costs<br />

are reflective of the known engineering issues at the <strong>Kangaroo</strong> <strong>Island</strong> <strong>Airport</strong>. For a<br />

more detailed break-down of the costs see Appendix D of the Tonkin Consulting report.<br />

Cost description Option 3<br />

Cost Estimate<br />

($’000)<br />

Option 2<br />

Cost Estimate<br />

($’000)<br />

Civil Works<br />

‐ Preliminaries 930 615<br />

‐ Site preparation and earthworks 402 72<br />

‐ Stormwater 634 135<br />

‐ Pavements (runway and apron) 5,850 2,436<br />

‐ Lighting (runway, apron and taxiway) 544 363<br />

‐ Building (terminal and upgrade of refuelling<br />

facility)<br />

4,492 3,917<br />

‐ Detailed design fees 600 400<br />

Total civil works (ex GST) 13,453 7,938<br />

Contingencies (12.5%) 1,682 992<br />

Total civil works inc Contingencies (ex GST) 15,134 8,931<br />

GST (10%) 1,513 893<br />

Construction Industry Training Board (CITB) levy<br />

(0.25%)<br />

42 25<br />

Grand total (inc GST and CITB levy) 16,689 9,848<br />

Source: Tonkin Consulting 2012<br />

In developing the cost estimates, the <strong>Council</strong> has estimated the costs associated with<br />

project management, tendering, risk management and associated <strong>Council</strong> activities as<br />

set out below.<br />

May 2013<br />

47