<strong>Kangaroo</strong> <strong>Island</strong> <strong>Airport</strong> Upgrade <strong>Business</strong> <strong>Case</strong><br />
allowances for construction on the <strong>Island</strong>. The below table provides a breakdown of<br />
the costs and demonstrates that the major cost items are pavement upgrade and<br />
terminal upgrade. A contingency of 12.5% has also been included as part of the<br />
calculation. Whilst a contingency is included, and highly appropriate for this exercise,<br />
the cost estimates have been prepared after site inspection, and onsite engineering<br />
assessments of the drainage culverts running under the runway. Therefore the costs<br />
are reflective of the known engineering issues at the <strong>Kangaroo</strong> <strong>Island</strong> <strong>Airport</strong>. For a<br />
more detailed break-down of the costs see Appendix D of the Tonkin Consulting report.<br />
Cost description Option 3<br />
Cost Estimate<br />
($’000)<br />
Option 2<br />
Cost Estimate<br />
($’000)<br />
Civil Works<br />
‐ Preliminaries 930 615<br />
‐ Site preparation and earthworks 402 72<br />
‐ Stormwater 634 135<br />
‐ Pavements (runway and apron) 5,850 2,436<br />
‐ Lighting (runway, apron and taxiway) 544 363<br />
‐ Building (terminal and upgrade of refuelling<br />
facility)<br />
4,492 3,917<br />
‐ Detailed design fees 600 400<br />
Total civil works (ex GST) 13,453 7,938<br />
Contingencies (12.5%) 1,682 992<br />
Total civil works inc Contingencies (ex GST) 15,134 8,931<br />
GST (10%) 1,513 893<br />
Construction Industry Training Board (CITB) levy<br />
(0.25%)<br />
42 25<br />
Grand total (inc GST and CITB levy) 16,689 9,848<br />
Source: Tonkin Consulting 2012<br />
In developing the cost estimates, the <strong>Council</strong> has estimated the costs associated with<br />
project management, tendering, risk management and associated <strong>Council</strong> activities as<br />
set out below.<br />