APPENDIX 1/5: TESTING TO BE CARRIED OUT BY THE CONTRACTOR (CONTINUED)<br />
Clause Work, Goods or Materials Test Frequency of Testing Test Certificate Comments<br />
Series 3000<br />
3001 General Inspection Reports as<br />
required in Appendix 30/1<br />
3005 Grass seeding,<br />
Rate of spread of fertilizer<br />
1 per 1000 square<br />
Wildflower seeding and<br />
metres<br />
turfing<br />
Rate of spread of seeding<br />
1 per 1000 square<br />
††<br />
metres<br />
Chemical analysis of fertilizer<br />
1 per source<br />
Grass seed germination and purity<br />
1 per source and mix<br />
Required prior to<br />
†<br />
(Official Seed Testing Station<br />
variety<br />
sowing<br />
tests)<br />
1 Unless otherwise stated above, all sampling and testing in this Appendix shall be by the<br />
Contractor.<br />
2 Tests comparable to those specified in this Appendix will be necessary for any equivalent work,<br />
goods or materials proposed by the Contractor (See sub-Clause 105.4).<br />
3 (11/03) (N) indicates that a UKAS or equivalent accredited laboratory sampling and test report or<br />
certificate is required.<br />
4 Unless otherwise shown in this Appendix tests for work, goods or materials as scheduled under<br />
any one Clause are required for all such work, goods or materials in the Works.<br />
5 Cube strength tests are not required for concrete complying with Clause 2602.<br />
6 Unless otherwise shown in this Appendix test certificates for work, goods or materials as<br />
scheduled under any one Clause are required for all such work, goods or materials in the Works.<br />