Method Statements and Check Lists must be prepared for every construction operation and submitted to<br />

the Engineer for comment no later than 10 days prior to commencement of any associated work or activity.<br />

Hold points must be identified to allow for checking and material testing at appropriate points. Where<br />

required hold points must be inserted to allow the Engineers representative to check materials and the<br />

Works. Work may not proceed until the Engineers Representative has given his consent to proceed.<br />

The Contractor must identify an individual to act as resident Quality Manager on site. This need not be a<br />

full time appointment but adequate time must be allowed for his activities. Independent Audits covering<br />

Quality and Health and Safety from their office based staff are to take place at monthly intervals as a<br />

minimum.<br />

2 ENVIRONMENTAL MANAGEMENT SYSTEM<br />

The Contractor shall institute and maintain, during the construction of the Works and environmental<br />

management system. This shall define the responsibilities, practices and procedures provided for<br />

environmental management and shall form part of the Quality Management Plan as detailed in this<br />

Appendix 1/24 of the Specification.<br />

It shall be developed to avoid wherever possible environmental accidents and pollution to encourage<br />

reduced consumption of resources, to restrict the production of waste and to promote good relationships<br />

with the relevant authorities. Commitments made regarding mitigation, their implementation and<br />

subsequent monitoring shall be recorded.<br />

Notwithstanding any other requirements of the Contract, the Environmental Management System shall:<br />

a. Include site specific Method Statements for all operations where there is a risk of<br />

environmental damage. These shall show how the proposed methods of construction<br />

shall restrict impacts on the environment, and how contingency plans and emergency<br />

procedures shall limit damage caused by accidents, spillage or any other unforeseen<br />

events. The Method Statements shall include notification procedures to the relevant<br />

authorities;<br />

b. Ensure that the Contractor shall submit to the Engineer details of the Environmental<br />

Management System and Method Statements for approval in advance of the<br />

construction of the Works. The Works shall not be commenced without such approval<br />

having being obtained in writing from the Engineer.<br />

c. The Contractor will liaise with the local community during the Contract. This shall<br />

include providing information about activities likely to give rise to nuisance, and a<br />

telephone number for complaints to be registered. A log of all complaints and follow up<br />

actions shall be kept and made available for inspection by the Engineer.<br />

3 SUBMISSION OF INFORMATION TO PROJECT MANAGER<br />