SECTION B - Derry City Council
SECTION B - Derry City Council
SECTION B - Derry City Council
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
APPENDIX 1/13: PROGRAMME OF WORKS<br />
1 The Contractor shall submit to the Project Manager three copies of a Construction Programme in<br />
the form of a bar chart approved by the Project Manager after the acceptance of the Tender and<br />
before he commences work on Site. It shall show the level of detail appropriate to each stage of the<br />
Works and all activities and restraints each of which shall be given a short title. All events shall be<br />
numbered and annotated with earliest and latest event dates.<br />
At the time of submission of the programme the contractor shall also provide a mass-haul diagram<br />
showing his intended earthworks movements and locations<br />
2 It shall cover all activities and delivery to Site of materials. No work shall start until the programme<br />
has been approved by the Project Manager.<br />
2 The Contractor shall record progress on the programme fortnightly in a manner approved by the<br />
Project Manager and submit the marked up programme to the Project managers representative<br />
for approval prior to site progress meeting along with a detailed site progress report.<br />
4 The programme shall be re-drawn on the instructions of the Project Manager should any<br />
circumstances arise which substantially alter the existing programme. Three copies of any<br />
revised programme shall be submitted to the Project Manager for approval.<br />
5 The approval of any programme by the Project Manager will neither effect the Contract Date of<br />
completion nor relieve the Contractor of his responsibilities to complete the Works by this date.<br />
6 The Contractor’s programme shall take into account the following constraints:<br />
• Constructing 1.85m high fencing around areas with Japanese knotweed as shown on the<br />
drawings before any other works can start.<br />
• Excavating out the area of Japanese knotweed indicated on the drawing and its disposal in<br />
a hoarded area<br />
• Keeping all existing cemetery footpaths and roads outside the site extent open at all times.<br />
• Maintaining access within the existing cemetery site at all times for <strong>Derry</strong> <strong>City</strong> <strong>Council</strong><br />
staff, as necessary<br />
• All public, bank and trade holidays.<br />
• Restrictions on site working hours, including ‘Quite Times’ on site during burials, see 7<br />
below for further details.<br />
• Traffic safety and management including notice requirements.<br />
• All other statutory notification periods<br />
• Work to privately and publicly owned services and supplies<br />
• Trials, tests and demonstrations prior to work items.<br />
• Compliance with technical approval procedures in relation to structures designed by the<br />
164