APPENDIX 1/12: SETTING OUT AND EXISTING GROUND LEVELS<br />

1.12.1 The locations of known points to be used for setting out purposes will be identified on site.<br />

1.12.2 The Contractor should note that the levels indicated on the Drawings are to Belfast Ordnance Datum. The<br />

Contractor shall set up a bench mark on site in agreement with the Project Manager.<br />

1.12.3 All contractors are advised to visit the site during the tender period (i.e. by appointment with the Employer)<br />

to fully acquaint themselves with the layout/topography of the site, and any restrictions with regard to<br />

ingress/egress to the site and restrictions within working area of the site.<br />

1.12.4 The Contractor shall be responsible for setting out all work and no kerbs, concrete, or bituminous material<br />

shall be laid until the Contractor has satisfied himself that the finished surface shall have sufficient falls to<br />

prevent water from ponding. The setting out may be checked by the Project Manager and any defect shall<br />

be rectified at the Contractor’s expense.<br />