Hills Cement Co. Limited.<br />

The pattern of drilling and blasting has been designed as follows:<br />

Proposed bench height : 6.0m<br />

Proposed diameter of hole : 100 mm,<br />

Effective depth of hole : 7.0m<br />

To maintain good fragmentation<br />

for quick removal of blasted<br />

muck, suggested burden : 3-3.5m<br />

Spacing : 4.0-4.5m<br />

Stemming column : 3.0-3.5m<br />

Tonnage of rock per hole : 236 tonnes.<br />

Impact on stability of slopes<br />

Rock slides in and around the vicinity-<br />

There are no visible signs of rock slides around the vicinity of the mine<br />

and no tension cracks or loosened boulders are present. The mining<br />

activity will have adverse impact on the slope stability, if appropriate<br />

control measures are not adopted. <strong>Control</strong>led blasting shall be adopted<br />

to avoid tension cracks and back breaks. Such crack filled with water<br />

reduces stability of excavated slopes and angle of slopes. Good<br />

drainage shall be provided in and around the quarry.<br />

Rolling boulders<br />

When mining of a bench reaches the edge of the hill, it may give rise to<br />

rolling of boulders downwards along the hill slopes. It may have<br />

adverse impacts on flora and structures on the way. It may also lead to<br />

serious injuries to human beings or animals. Adequate control<br />

measures as given below have been proposed to prevent this<br />

phenoena.<br />

On end bench 8m from the edge is to be considered as “Caution Zone”.<br />

Regular mining shall not be done in the zone. The orientation of the<br />

face will be kept parallel to the edge of the hill in the area and the<br />

bench height is restricted to 2m only. <strong>Control</strong>led blasting will be<br />

adopted for the last blast. Pre-splitting will be done, if required.<br />

<strong>Pollution</strong> <strong>Control</strong> Consultants (India) Pvt. Ltd. 78