February 1997AFPMB TIM #39GPWS-QA Guiderequirement is satisfactory. If the ODR is less than ½ the MADR, the QAE should recommend to theCOR to notify the Contractor that per<strong>for</strong>mance is excellent and to keep up the good work. Considerusing reduced surveillance <strong>for</strong> the coming evaluation period.b. If the ODR <strong>for</strong> a work requirement is greater than the MADR, overall per<strong>for</strong>mance of thatrequirement is unsatisfactory and the QAE should recommend to the COR that a CDR be issued to theContractor, or that stronger action be taken. Increased surveillance should be used <strong>for</strong> the comingevaluation period (see paragraph 5 above).QA-41