13.07.2015 Views

Guidelines for Preparing DoD Pest Control Contracts Using ...

Guidelines for Preparing DoD Pest Control Contracts Using ...

Guidelines for Preparing DoD Pest Control Contracts Using ...

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

February 1997AFPMB TIM #39GPWS-QA Guiderequirement is satisfactory. If the ODR is less than ½ the MADR, the QAE should recommend to theCOR to notify the Contractor that per<strong>for</strong>mance is excellent and to keep up the good work. Considerusing reduced surveillance <strong>for</strong> the coming evaluation period.b. If the ODR <strong>for</strong> a work requirement is greater than the MADR, overall per<strong>for</strong>mance of thatrequirement is unsatisfactory and the QAE should recommend to the COR that a CDR be issued to theContractor, or that stronger action be taken. Increased surveillance should be used <strong>for</strong> the comingevaluation period (see paragraph 5 above).QA-41

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!