Supply, Installation, Configuration & Integration of IT infrastructure <strong>for</strong> State Data Center, e-Secretariat<br />
& Other Projects [NIB No. F5(776)/DoIT/Tech/13/I/10766/2013 dated 23-08-2013]<br />
7. SPECIAL TERMS AND CONDITIONS OF TENDER & CONTRACT<br />
1) Payment Terms and Schedule<br />
a) Payment schedule - Payments to the SI, after successful completion of the specified<br />
project deliverables & related services as per SoW, would be made as under: -<br />
S.No. Milestone Deliverables Payable Amount<br />
1. Implementation<br />
Phase<br />
2. Testing &<br />
Commissioning<br />
Phase<br />
3. Warranty/software<br />
Support Services<br />
<strong>for</strong> a period of 3<br />
Years<br />
Delivery Challan<br />
OEM Warranty Certificates <strong>for</strong><br />
Hardware items<br />
OEM Software Support /<br />
Assurance Certificate<br />
Inspection Report by DoIT&C<br />
Installation Reports,<br />
Acceptance Test Report by<br />
DoIT&C<br />
Quarterly SLA attainment<br />
reports<br />
70% of total value of actual items<br />
delivered & inspected<br />
12% of total value of actual items<br />
tested, installed and commissioned.<br />
[In case, an item is not installed even<br />
after 2 months of <strong>supply</strong>, where the<br />
delay is not on the part of the supplier,<br />
it will be treated as commissioned <strong>for</strong><br />
the purpose of releasing payment]<br />
Remaining 18% of total value of actual<br />
items tested and commissioned (as<br />
applicable) in 12 equated quarterly<br />
installments over a period of 3 years<br />
i.e. 1.5% per quarter <strong>for</strong> Package A & B<br />
and 8 equated quarterly installments<br />
over a period of 2 years i.e. 2.25% per<br />
quarter <strong>for</strong> packages C & D at the end<br />
of each quarter and upon submission<br />
of invoice/bills (in triplicate) along with<br />
all supporting documents<br />
b) The supplier’s/ selected bidder’s request <strong>for</strong> payment shall be made to the purchaser in<br />
writing, accompanied by invoices describing, as appropriate, the goods delivered and<br />
related services per<strong>for</strong>med, and by the required documents submitted pursuant to general<br />
conditions of the contract and upon fulfilment of all the obligations stipulated in the<br />
Contract.<br />
c) Due payments shall be made promptly by the purchaser, generally within sixty (60) days<br />
after submission of an invoice or request <strong>for</strong> payment by the supplier/ selected bidder,<br />
subject to successful execution of work to the satisfaction of the purchaser.<br />
d) The currency or currencies in which payments shall be made to the supplier/ selected<br />
bidder under this Contract shall be Indian Rupees (INR) only.<br />
e) All remittance charges will be borne by the supplier/ selected bidder.<br />
f) In case of disputed items, the disputed amount shall be withheld and will be paid only after<br />
settlement of the dispute.<br />
Page 57 of 88