PROJECT DESCRIPTION<br />

Project Status at<br />

30 June 20<strong>15</strong><br />

END OF YEAR REVIEW (APR – JUNE 20<strong>15</strong>)<br />

Budget<br />

Risks & Issues<br />

COMMENTS AND CORRECTIVE<br />

ACTIONS FOR THOSE PROJECTS<br />

UNDER TARGET<br />

Adjusted Budget<br />

<strong>2014</strong>/20<strong>15</strong> ($ Million)<br />

Actual Spent as At 30<br />

June 20<strong>15</strong> ($ Million)<br />

% Actual Spent<br />

Committed<br />

20<strong>15</strong>/16 ($ Million)<br />

Society<br />

Passive Park<br />

Passive Park Development<br />

Cheltondale Park, Madeley<br />

Park.<br />

On Target<br />

n/a. 268 252 94% 13<br />

Develop Passive Parks<br />

Tendring Girrawheen.<br />

Completed<br />

Project was completed in<br />

August <strong>2014</strong>.<br />

107 107 100% 0<br />

Salitage Park Pearsall –<br />

Development of Passive<br />

Park.<br />

Under Target<br />

Preliminary design undertaken to<br />

facilitate advancement of irrigation<br />

bore construction. Concept design<br />

and public consultation scheduled for<br />

completion by November 20<strong>15</strong>.<br />

To be completed in the 20<strong>15</strong>/16 year<br />

because of additional funding being<br />

allocated to the project.<br />

160 40 25% 19<br />

Sport Facilities<br />

Yanchep District Sports<br />

Amenities – Yanchep<br />

District Sports Amenities<br />

Building Stage 1 –<br />

Yanchep/Two Rocks sports<br />

amenities building design,<br />

documentation and stage<br />

1 of construction.<br />

On Target<br />

The delay is due to additional time<br />

required to finalise the Yanchep-Two<br />

Rocks Developer Contribution Plan<br />

(DCP), obtain Council endorsement<br />

of the Marmion Ave Extension and<br />

Oval Groundwork’s costs, and await<br />

the end of the appeals period for<br />

the DCP. This process delayed the<br />

project by six (6) months, in the main<br />

due to the requirements of the Deed<br />

of Agreement between the City<br />

and Yanchep Beach Joint Venture.<br />

Construction works for the access<br />

road and groundworks commenced<br />

in June 20<strong>15</strong>. Design of the active<br />

sports field and the community<br />

building is scheduled to be completed<br />

by December 20<strong>15</strong> and following<br />

the appointment of a contractor,<br />

construction works are likely to<br />

commence in March 2016.<br />

<strong>15</strong>0 29 19% 0<br />

| ANNUAL REPORT <strong>2014</strong>/20<strong>15</strong> | CITY OF WANNEROO | OUR PERFORMANCE<br />