9. 06. Avvik fra kalkyle.<br />

Kalkulerte byggekostnader i 1998. kr. 2 422 800<br />

Prisstigning fra sept. 1998 til sept. 2005.<br />

i hht. SSB – 26,3% for enebolig i tre. kr. 637 196<br />

Kalkulerte byggekostnader justert for prisstigning ca. kr. 3 060 000<br />

Byggekostnadene i 2005 for bygning 4e ble ca kr. 210 000 eller ca 7% høyere<br />

enn det beløpet som var kalkulert i 1998. I fht. kalkylene ble det fornyet en god<br />

del mer lafteplank i tømmerkassen enn beregnet. Dette var tidkrevende arbeide. I<br />

tillegg gikk det nok noe mertid på at istandsettingen ble gjennomført som et<br />

pilotprosjekt.<br />

Stiftelsen Bryggen<br />

arkitekt E.Mørk<br />

09.11.2006.<br />

Rev. 26.11.07.<br />

Rev. 06.03.08.<br />

SUMMARY.<br />

The Bryggen Project.<br />

The Bryggen Project started in 2000 as a repair/restoration programme for the suite of wooden<br />

buildings that makes up the World Heritage Site of Bryggen. The project’s objective is to raise the<br />

standard of the buildings to a level where their future upkeep will require no more than ordinary<br />

maintenance.<br />

Building no 4e in the Svensgården tenement.<br />

Bryggen is the remaining part of an ancient warehouse quarter on the eastern shore of Vågen, the<br />

central harbour of Bergen. Within the site there are 61 listed building, most of them reconstructed<br />

in wood after the city fire in 1702.<br />

Building no 4e is one of the site’s smallest buildings, consisting of a timber casing with a single<br />

ground-floor room of 5 by 6 metres and a height of 3.3 metres (the longitudinal axis runs<br />

perpendicular to the waterfront). The casing is built up of timber planks fitted on top of each other<br />

and corner-jointed. The attic was replaced by a simple rafter structure with sheet-metal roofing.<br />

The foundations are single, shallow, dry-stone walls laid on the ground.<br />

Documentation and surveying.<br />

The basic documentation was done by “hand-measurement” of the building at a scale of 1:20, with<br />

the use of x, y and z grid lines laid out with white string. This was supplemented with systematic<br />

photographic recording of all elements. All photos are catalogued with a map showing the position<br />

of the camera and a written description of the motif.<br />

The technical survey of the building comprised a written description of all the individual elements<br />

and their state of repair. Damages to elements are noted on a set of the survey drawings, along<br />

with an estimate of the age of each element. The summary for research and development purposes<br />

at the back of this report also gives a detailed description of the chronology of the former<br />

interventions and the technical condition of the building.<br />

The state of repair.<br />

The building was generally in a very poor state of repair before its restoration started. The attic and<br />

roof had been replaced by a simple provisional structure with modern wooden elements supporting<br />

a roofing of corrugated iron. The timber walls in the casing were tied together at the corners by<br />

provisional uprights inside and outside, the pairs of uprights being fastened together with modern<br />

48

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!