J.11 APPROVAL OF A PROPOSED CHANGE ORDER (NO. FIVE)<br />
TO THE CONTRACT FOR THE CONSTRUCTION AT<br />
WELLINGTON ELEMENTARY SCHOOL<br />
(THE NEW ELEMENTARY SCHOOL AT KEITHSHIRE WAY)<br />
BG 09-267<br />
BACKGROUND AND RATIONALE: The construction <strong>of</strong> a new elementary school to be located on 14.07<br />
acres (donated by NDC) at 3280 Keithshire Way is listed as priority 1a.1 on FCPS's District Facility Plan.<br />
GBBN Architects has produced Construction Documents (plans, specifications, bidding requirements,<br />
etc.) describing the construction <strong>of</strong> a new school totaling approximately 72,000 SF to serve 650 students<br />
based upon FCPS elementary school program standards. Bids were received on March 18, 2010 and<br />
construction began in April, 2010. The Department <strong>of</strong> Physical Support Services, the design consultants<br />
and the local building code <strong>of</strong>ficials have reviewed the progress <strong>of</strong> the work. Changes to the original plans<br />
and specifications have been necessary in order to satisfy the requirements described below. Approval <strong>of</strong><br />
these changes allows the work to be completed.<br />
COST: The description and cost <strong>of</strong> these items are summarized as follows:<br />
To improve original plans and specs:<br />
Delete one Solatube at Health Clinic and credit to one<br />
DPO (Shaffner Heaney) ; deduct:<br />
Provide labor, materials and equipment to add spray<br />
insulation to provide weather-tight seal at top <strong>of</strong><br />
exterior walls in Library and Gym; add:<br />
Provide labor, materials and equipment to provide<br />
acoustical insulation to reduce noise from vacuum<br />
pump in Janitor’s Closet into adjacent classroom;<br />
add:<br />
Provide labor, materials and equipment to provide<br />
five stainless steel corner guards due to sharp cut<br />
edges <strong>of</strong> the concrete block; add:<br />
Provide labor, materials and equipment to provide<br />
one additional steel handrail to Mezzanine stair for<br />
safety; add:<br />
To comply with building code:<br />
Provide labor, materials and equipment to provide a<br />
storage tank with a booster pump for rain water<br />
collection system as required by Ky. Division <strong>of</strong><br />
Plumbing: add:<br />
To resolve unforeseen conflict:<br />
Provide labor, materials and equipment to provide<br />
condensate pumps to drain VRF units as gravity<br />
draining will not work; add:<br />
Provide labor, materials and equipment to provide the<br />
difference between the water meter allowance and<br />
the Kentucky American Water actual charge; add:<br />
Change to<br />
DPOs<br />
($720.00)<br />
Change to<br />
GC Contract<br />
($500.00)<br />
$5,508.50<br />
$2,842.55<br />
$2,342.34<br />
$943.00<br />
$22,933.39<br />
$3,570.41<br />
$936.10<br />
82 April 25, 2011<br />
5.2% A/E<br />
FEE<br />
$0<br />
$0<br />
$0<br />
$0<br />
$0<br />
$1,192.54<br />
$185.66<br />
$48.68<br />
Total Change Order No. Five: ($720.00) $38,576.29<br />
Design consultant fees: $1,426.88<br />
Total Cost: $39,283.17