J.11 APPROVAL OF A PROPOSED CHANGE ORDER (NO. FIVE)<br />

TO THE CONTRACT FOR THE CONSTRUCTION AT<br />

WELLINGTON ELEMENTARY SCHOOL<br />

(THE NEW ELEMENTARY SCHOOL AT KEITHSHIRE WAY)<br />

BG 09-267<br />

BACKGROUND AND RATIONALE: The construction <strong>of</strong> a new elementary school to be located on 14.07<br />

acres (donated by NDC) at 3280 Keithshire Way is listed as priority 1a.1 on FCPS's District Facility Plan.<br />

GBBN Architects has produced Construction Documents (plans, specifications, bidding requirements,<br />

etc.) describing the construction <strong>of</strong> a new school totaling approximately 72,000 SF to serve 650 students<br />

based upon FCPS elementary school program standards. Bids were received on March 18, 2010 and<br />

construction began in April, 2010. The Department <strong>of</strong> Physical Support Services, the design consultants<br />

and the local building code <strong>of</strong>ficials have reviewed the progress <strong>of</strong> the work. Changes to the original plans<br />

and specifications have been necessary in order to satisfy the requirements described below. Approval <strong>of</strong><br />

these changes allows the work to be completed.<br />

COST: The description and cost <strong>of</strong> these items are summarized as follows:<br />

To improve original plans and specs:<br />

Delete one Solatube at Health Clinic and credit to one<br />

DPO (Shaffner Heaney) ; deduct:<br />

Provide labor, materials and equipment to add spray<br />

insulation to provide weather-tight seal at top <strong>of</strong><br />

exterior walls in Library and Gym; add:<br />

Provide labor, materials and equipment to provide<br />

acoustical insulation to reduce noise from vacuum<br />

pump in Janitor’s Closet into adjacent classroom;<br />

add:<br />

Provide labor, materials and equipment to provide<br />

five stainless steel corner guards due to sharp cut<br />

edges <strong>of</strong> the concrete block; add:<br />

Provide labor, materials and equipment to provide<br />

one additional steel handrail to Mezzanine stair for<br />

safety; add:<br />

To comply with building code:<br />

Provide labor, materials and equipment to provide a<br />

storage tank with a booster pump for rain water<br />

collection system as required by Ky. Division <strong>of</strong><br />

Plumbing: add:<br />

To resolve unforeseen conflict:<br />

Provide labor, materials and equipment to provide<br />

condensate pumps to drain VRF units as gravity<br />

draining will not work; add:<br />

Provide labor, materials and equipment to provide the<br />

difference between the water meter allowance and<br />

the Kentucky American Water actual charge; add:<br />

Change to<br />

DPOs<br />

($720.00)<br />

Change to<br />

GC Contract<br />

($500.00)<br />

$5,508.50<br />

$2,842.55<br />

$2,342.34<br />

$943.00<br />

$22,933.39<br />

$3,570.41<br />

$936.10<br />

82 April 25, 2011<br />

5.2% A/E<br />

FEE<br />

$0<br />

$0<br />

$0<br />

$0<br />

$0<br />

$1,192.54<br />

$185.66<br />

$48.68<br />

Total Change Order No. Five: ($720.00) $38,576.29<br />

Design consultant fees: $1,426.88<br />

Total Cost: $39,283.17