07.04.2013 Views

Fayette County Board of Education - Fayette County Public Schools

Fayette County Board of Education - Fayette County Public Schools

Fayette County Board of Education - Fayette County Public Schools

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

K.19 APPROVAL OF A BG-1 PROJECT APPLICATION FOR THE<br />

RENOVATION OF STONEWALL ELEMENTARY SCHOOL<br />

BACKGROUND AND RATIONALE: The renovation <strong>of</strong> the existing Stonewall Elementary School is listed<br />

as priority 2c.3 on FCPS’s 2009 District Facility Plan. The Director <strong>of</strong> Facility Design and Construction has<br />

drafted a preliminary cost estimate for the renovation <strong>of</strong> the existing building and the construction <strong>of</strong> a<br />

small addition, yielding a final project <strong>of</strong> approximately 77,708 SF to serve 775 students. The program is<br />

consistent with other recent FCPS elementary school projects. Project cost estimates are based on the<br />

most recent construction bids and include: design and financing fees; furnishings; surveys; and other<br />

miscellaneous costs. The project design must begin now in order to meet an expected completion date <strong>of</strong><br />

late 2013. The <strong>Board</strong> approved Tate Hill Jacobs Architects as the design consultant for this project at its<br />

February 28, 2011 meeting.<br />

PROPOSAL: Based on the rationale above, a BG-1 Project Application is required as follows:<br />

Initial BG-1 Project Application Budget<br />

Total Construction Cost: $12,433,280<br />

Architect/Engineer Fee: $768,902<br />

Bond Discount: $257,139<br />

Fiscal Agent Fee: $97,658<br />

Contingencies: $621,664<br />

Site Acquisition: -<br />

Furnishings/Equipment: $675,000<br />

Furnishings/Computers: $208,000<br />

HVAC Balancing & Asbestos Abatement $74,800<br />

Technology Network Systems (KETS), telephone, etc.: $35,000<br />

Surveys, Printing, etc.: $50,000<br />

Special Inspections: $50,000<br />

Pr<strong>of</strong>essional Services: $20,000<br />

Total Estimated Cost: $15,291,443<br />

FUNDING SOURCE:<br />

Fund Org. Code Object Code Balance<br />

Building Fund 0003213 0840 $1,000,000<br />

Local Bond 360 5110 $14,291,443<br />

STAFF CONTACT: William R. Wallace, AIA, Director, Facility Design & Construction @ 381.3824<br />

REFERENCE: 702 KAR 4:160<br />

RECOMMENDATION: A motion is in order to:<br />

“approve a BG-1 Project Application for the renovation and addition at Stonewall Elementary School in the<br />

amount <strong>of</strong> $15,291,443 (Fifteen Million, Two Hundred Ninety-one Thousand, Four Hundred Forty-three<br />

Dollars), subject to the approval <strong>of</strong> the Kentucky Department <strong>of</strong> <strong>Education</strong>, District Facilities Branch, per<br />

the provisions <strong>of</strong> 702 KAR 4:160.”<br />

On a motion by ______________________, and seconded by ____________________, the <strong>Board</strong><br />

approves a BG-1 Project Application for the renovation and addition at Stonewall Elementary School in the<br />

amount <strong>of</strong> $15,291,443 (Fifteen Million, Two Hundred Ninety-one Thousand, Four Hundred Forty-three<br />

Dollars), subject to the approval <strong>of</strong> the Kentucky Department <strong>of</strong> <strong>Education</strong>, District Facilities Branch, per<br />

the provisions <strong>of</strong> 702 KAR 4:160.<br />

______________________________________ _____________________________________<br />

John Price, Chair Stuart M. Silberman, Superintendent<br />

95 April 25, 2011

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!