K.22 APPROVAL OF BID, INTERIM AND PROPOSED CONTRACTS, AND A<br />

REVISION TO THE BG-1 PROJECT APPLICATION FOR THE RENOVATION<br />

OF MILLCREEK ELEMENTARY SCHOOL<br />

BG 10-259<br />

BACKGROUND AND RATIONALE: The renovation <strong>of</strong> the existing Millcreek Elementary School is listed as<br />

priority 1c.7 on FCPS’s 2009 District Facility Plan. Pearson & Peters Architects produced final Construction<br />

Documents for bidding describing a renovation <strong>of</strong> the existing building and the construction <strong>of</strong> an addition totaling<br />

approximately 70,000 SF to serve 625 students. The program is consistent with other recent FCPS elementary<br />

school projects. The design consultants’ last BG-3 Statement <strong>of</strong> Probable Cost estimated the construction cost to<br />

be $12,216,577. The project is planned to start construction around June 6, 2011. Portions <strong>of</strong> the building will be<br />

vacated in three phases to complete the work while instructional activities continue. Final completion is planned for<br />

August, 2012. On Thursday, April 14, 2011, four general contractors submitted proposals on a base bid and 10<br />

alternate bids. The results <strong>of</strong> the bidding are as follows:<br />

Alternate Bid Nos. BASE BID plus Nos.<br />

BIDDER BASE BID 1, 3, 4, 5, 6, 7, 8, 9 & 10 1, 3, 4, 5, 6, 7, 8, 9 & 10<br />

1 Preston Construction $8,593,000 $179,700 $8,772,700<br />

2 D.W. Wilburn, Inc. $8,800,000 $169,400 $8,969,400<br />

3 Isaac Tatum Construction $8,780,000 $203,000 $8,983,000<br />

4 Alliance Corporation $8,909,414 $169,000 $9,078,414<br />

Alternate #1= Hardware Manufacturer; Alternate #2=Plastic Laminate Casework; Alternate #3=HVAC Manufacturer; Alternate #4=Controls<br />

Manufacturer; Alternate #5=Security Alarm Manufacturer; Alternate #6=Fire Alarm Equipment Manufacturer; Alternate #7=PA System<br />

Manufacturer; Alternate #8=Food Service Equip. Manufacturer; Alternate #9=Gym Floor; Alternate #10=Terrazzo Floor<br />

PROPOSAL: Based on the review <strong>of</strong> these proposals, the FCPS staff and the design consultants recommend<br />

acceptance <strong>of</strong> the base bid <strong>of</strong> $8,593,000, plus Alternates 1, 3, 4, 5, 6, 7, 8, 9 and 10 for $179,700. This would<br />

bring the value <strong>of</strong> the proposed total general construction contract with Preston Construction to $8,772,700<br />

(21.55% below the BG-3 estimate). An existing separate price contract with U.S. Specialties, a KEDC vendor,<br />

allows FCPS to purchase the higher quality plastic laminate casework for the project for a combined total <strong>of</strong><br />

$129,449, a savings <strong>of</strong> $3,051 over Alternate 2 submitted. This eliminates the need to accept Alternate 2. The<br />

FCPS staff and the design consultants recommend approval <strong>of</strong> the proposed contract and revised BG-1. Upon the<br />

<strong>Board</strong>’s approval, these documents will be submitted to the KDE District Facilities Branch for review and approval.<br />

Approval will allow the award <strong>of</strong> a contract and renovation <strong>of</strong> Millcreek Elementary School to commence with<br />

minimal delay. In order to take advantage <strong>of</strong> lower financing costs, the bond sale for this project will be combined<br />

with the bond sale for the renovations <strong>of</strong> Breckinridge, Cardinal Valley, Clays Mill and Mary Todd Elementary<br />

<strong>Schools</strong> in May, 2011. An interim contract will be required until bond proceeds are available. Based on this<br />

recommendation, a revision to the BG-1 is required as follows:<br />

Revised BG-1 Total Proposed BG-1<br />

(4/10)<br />

Revision Total<br />

Total Construction Cost: $12,216,577 $8,772,700<br />

Architect/Engineer Fee: $739,229 $620,388<br />

Bond Discount: $247,829 $166,160<br />

Fiscal Agent Fee: $96,194 $3,285<br />

Contingencies: $610,829 $438,635<br />

Furnishings/Equipment: $525,000 $597,692<br />

Furnishings/Computers: $100,000 $173,903<br />

HVAC Balancing & Asbestos Abatement $65,000 $65,000<br />

Technology Network Systems (KETS), telephone, etc.: $45,000 $35,000<br />

Surveys, Printing, Advertisement, etc.: $50,000 $50,000<br />

Special Inspections: $13,178 $40,000<br />

Pr<strong>of</strong>essional Consultant: $20,000 $20,000<br />

99 April 25, 2011