J.13 APPROVAL OF A PROPOSED CHANGE ORDER (NO. NINE)<br />

TO THE CONTRACT FOR THE CONSTRUCTION OF THE<br />

LOCUST TRACE AGRISCIENCE FARM (PHASE 2)<br />

BG 09-339<br />

BACKGROUND AND RATIONALE: The construction <strong>of</strong> a new 225-student Agriscience education center<br />

to be located on 82.28 acres (surplus Federal property) on Leestown Road is listed as priority 1a.2 on<br />

FCPS’s 2009 District Facility Plan. A team lead by Tate Hill Jacobs Architects designed a preliminary<br />

building program for a classroom building <strong>of</strong> 43,081 sf and an arena building <strong>of</strong> 19,257 sf, for a total <strong>of</strong><br />

62,338 SF, based upon other recent FCPS technical school projects. A contract with Messer Construction<br />

Company in the amount <strong>of</strong> $14,930,200 was accepted and approved by the <strong>Board</strong> in a meeting held on<br />

June 28, 2010. The Department <strong>of</strong> Physical Support Services, the design consultants and the local<br />

building code <strong>of</strong>ficials have reviewed the progress <strong>of</strong> the work. Changes to the original plans and<br />

specifications have been necessary in order to satisfy the requirements described below. Approval <strong>of</strong><br />

these changes allows the work to be completed.<br />

COST: The description and cost <strong>of</strong> these items are summarized as follows:<br />

To improve original plans and specs:<br />

Provide labor, materials and equipment to install<br />

Owner-provided paper towel, toilet paper and soap<br />

dispensers; add:<br />

Credit to DPO (Overhead Door Co.) due to deletion <strong>of</strong><br />

cylinder locks on motorized overhead doors; deduct:<br />

Change to<br />

DPOs<br />

($1,036.00)<br />

Change to<br />

GC Contract<br />

$1,830.00<br />

86 April 25, 2011<br />

5.1% A/E<br />

FEE<br />

Total Change Order No. Nine: ($1,036.00) $1,830.00<br />

Design consultant fees: $0<br />

Total Cost: $794.00<br />

A 5% contingency ($746,510) is included in the project's available funds. There have been eight previous<br />

change orders on this project. The cost <strong>of</strong> the current and all changes orders represents a 2.07%<br />

increase in the construction cost.<br />

FUNDING SOURCE & BALANCE:<br />

Fund Organization Code Project Code Object Code Balance<br />

Construction 360 0003610 09339 0840 $377,260.70<br />

STAFF CONTACT: William R. Wallace, AIA, Director, Facility Design & Construction @ 381.3824<br />

REFERENCE: 702 KAR 4:160<br />

RECOMMENDATION: A motion is in order to:<br />

“approve the proposed additive Change Order No. Nine to the contract with Messer Construction<br />

Company, for the construction <strong>of</strong> Locust Trace Agriscience Farm (Phase 2) in the amount <strong>of</strong> $1,830.00<br />

(One Thousand, Eight Hundred Thirty Dollars) and a credit to the Direct Purchase Orders in the amount <strong>of</strong><br />

$1,036.00 (One Thousand, Thirty-six Dollars), subject to the approval <strong>of</strong> the Kentucky Department <strong>of</strong><br />

<strong>Education</strong>, District Facilities Branch, per the provisions <strong>of</strong> 702 KAR 4:160.”<br />

On motion by __________________________, seconded by ___________________________________,<br />

the <strong>Board</strong> approved the proposed additive Change Order No. Nine to the contract with Messer<br />

$0<br />