Final EIAR - Aurecon AME Environmental | Environmental Projects
Final EIAR - Aurecon AME Environmental | Environmental Projects
Final EIAR - Aurecon AME Environmental | Environmental Projects
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Proposed Wind and Solar (Photovoltaic) Energy Facilities on Kangnas Farm near Springbok in the Northern Cape: <strong>Final</strong> EIR 146<br />
Based on the significance of the potential impacts, summarised in Section 5.3 and 5.5, the EAP<br />
is of the opinion that the proposed wind and solar energy facilities and associated substations,<br />
including alternatives, being applied for be authorised as the benefits outweigh the negative<br />
environmental impacts. The significance of negative impacts can be reduced with effective and<br />
appropriate mitigation through a Life-Cycle EMP, as described in this report. If authorised, the<br />
implementation of an EMP should be included as a condition of approval.<br />
It should be noted that the Department of Energy’s (DoE) current renewable energy<br />
procurement program has capped the maximum size of wind and solar energy projects at 140<br />
MW and 75 MW respectively. While there has been no formal information about the project size<br />
cap being lifted various discussions within the industry to increase or remove the cap all<br />
together are taking place. The main drivers for lifting the cap would include:<br />
• Achieving the targets set by the Integrated Resource Plan (IRP) 2010 (11 400 MW of<br />
new build renewable energy). After the first two rounds of the DoE’s procurement<br />
process Eskom’s distribution grid is already getting congested and in locations where<br />
there is good wind and solar resource the distribution grid capacity will be limited and<br />
only smaller projects will be able to connect (< 30 MW). That will require larger projects<br />
to connect to Eskom’s transmission grid which is much more expensive and time<br />
consuming. To ensure affordable projects connecting to transmission grid, projects will<br />
need to be larger than the current caps to continue the current pricing levels as seen in<br />
Round 2;<br />
• To achieve the local economic development goals quicker and with larger impact;<br />
• To get more energy onto the grid at a faster pace to aid in ensuring South Africa’s<br />
energy security. South Africa will not be able to achieve the IRP targets with project<br />
sizes being limited by grid capacity and financial viability;<br />
• To ensure South Africa’s renewable energy becomes even more affordable.<br />
The Kangnas wind and solar projects have been developed at a large scale with a longer term<br />
vision that the project cap will be lifted. The wind and solar projects have been developed to<br />
allow for phases of 75 MW (solar) and 140 MW (wind) to allow the developer flexibility in the<br />
future to suit the future procurement requirements in terms of size.<br />
As the only grid connection for the Kangnas site is the Nama/Aggeneys 220 kV transmission<br />
line, a 140 MW wind or 75 MW solar project will not be competitive nor affordable.<br />
The minimum size for a wind project at the Kangnas site, which would be competitive and<br />
affordable and hence a viable option for DoE to select, would be 280 MW, thus two of the<br />
proposed four phases. Phase A and B would be preferred by the developer due to the superior<br />
resource and limited environmental impacts of these phases.<br />
The minimum size for a solar project at the Kangnas site, which would be competitive and<br />
affordable and hence a viable option for DoE to select, would be 225 MW, thus all three of the<br />
proposed phases.<br />
It should be noted that Eskom’s current future planning for the Nama/Aggeneys 220 kV line is to<br />
upgrade to 400 kV. Should Eskom embark on the 400 kV upgrade in the near future all four<br />
© <strong>Aurecon</strong> (2012) No unauthorised reproduction, copy<br />
or adaptation, in whole or in part, may be made.<br />
P:\<strong>Projects</strong>\108495 Kangnas WEF & PV EIA's\3 Project Delivery\4 Reports\FEIR\FEIR 210213 <strong>Final</strong>.doc