SRK Consulting: Project No: 439414 <strong>Staatsolie</strong> Pipeline <strong>EIA</strong> – Draft <strong>EIA</strong> Report Page 76<br />
that potential impacts of the project are minimised, and that the significance of those impacts is as<br />
predicted by the <strong>EIA</strong> process.<br />
Management and monitoring measures were developed from the recommendations and mitigation<br />
measures listed in the <strong>EIA</strong> Report (Section 6). The tables with mitigation measures relevant to the<br />
pipelines project are contained in the tables below. The measures in the EMMP are structured to<br />
facilitate their incorporation into tender documents and ease of on-site implementation.<br />
The mitigation measures should be implemented within the framework provided in the EMMP<br />
developed for the Refinery Expansion Project (SRK Report No. 398251/8, January 2010). That<br />
EMMP lays out a structure for the implementation of measures and the monitoring of and reporting<br />
on environmental performance. Generally, the EMMP is a living document and environmental<br />
management must be reviewed and adapted throughout the construction phase and lifetime of the<br />
pipeline to respond to specific operational circumstances.<br />
Mitigation measures apply to the following three phases of the pipelines project:<br />
• Design Phase: These measures relate to the detailed layout, planning and design of the<br />
pipelines and their alignment and associated infrastructure. They will largely be implemented by<br />
the planning and development team, prior to the commencement of any physical on-site<br />
activities. These mitigation measures are presented in Table 6-14.<br />
• Construction Phase: These mitigation measures are applicable during site preparation and<br />
laying of the pipelines. They must be implemented by the relevant contractors and subcontractors.<br />
These mitigation measures are presented in Table 6-15.<br />
• Operations Phase: These mitigation measures are applicable during the long-term operation of<br />
the pipelines and must be implemented by the relevant <strong>Staatsolie</strong> management team. These<br />
mitigation measures are presented in Table 6-16.<br />
REUT/DALC 439414_<strong>Staatsolie</strong>Pipeline<strong>EIA</strong>_Draft <strong>EIA</strong> Report_Final June 2012