12.07.2015 Views

The Challenge of Low-Carbon Development - World Bank Internet ...

The Challenge of Low-Carbon Development - World Bank Internet ...

The Challenge of Low-Carbon Development - World Bank Internet ...

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Box 2.3Mitigating Political Risks in Renewables: A MIGA caseIn 2000, an energy company was awarded a build-own-operate contract for a geothermal power plant in Africa,with rights to develop additional geothermal fields and expand capacity. <strong>The</strong> company signed a 20-year powerpurchase agreement with the national power utility, a parastatal. <strong>The</strong> average base generation tariff was slightlyhigher than the average cost for domestically produced electricity but lower than the cost <strong>of</strong> imported hydropowerfrom neighboring countries. <strong>The</strong> country has long suffered from power shortages, and in 2000, only 10 percent<strong>of</strong> the population had access to electricity.Major risks for the investor included currency transfer restrictions, government breach <strong>of</strong> obligations underthe power purchase agreement, and civil disturbances. MIGA provided the company (a repeat client) coverageagainst currency transfer restrictions, war and civil disturbance, and expropriation. Expropriation coverage insuresbroadly not only against the risk <strong>of</strong> outright seizure but also against breach <strong>of</strong> contract and other forms <strong>of</strong> de factoexpropriation.Shortly after MIGA issued the guarantee for Phase 1 <strong>of</strong> the project, the government attempted to renegotiatethe tariffs because the <strong>of</strong>f-taker’s power purchase price from the company, as agreed under the power purchaseagreement, was higher than the tariff it charged to end users. <strong>The</strong> government also refused to honor some <strong>of</strong> itscontractual obligations under the power purchase agreement. <strong>The</strong> dispute resulted in additional costs and delayedcompletion <strong>of</strong> the first phase <strong>of</strong> the project.MIGA worked with both parties over five years and played a crucial part in reaching a resolution. <strong>The</strong> <strong>World</strong> <strong>Bank</strong>’slong involvement in the sector—it had financed two adjacent geothermal plants—provided a foundation for thesediscussions. <strong>The</strong> disputes were resolved when the utility agreed to honor the existing power purchase agreementwithout price renegotiation. <strong>The</strong> investor considered MIGA’s guarantee as critical for the implementation <strong>of</strong> Phase1 <strong>of</strong> the project and, on resolving the dispute, obtained additional MIGA political risk insurance to cover expansion<strong>of</strong> the geothermal plant’s installed capacity.Source: IEG-MIGA.Over 2003–08, guarantees for grid-connected renewableenergy were $541 million, about 15 percent <strong>of</strong> WBGcommitments for grid-renewable energy. During this period,MIGA issued six guarantees for renewable energy projects.By far the largest guarantee was for the 1-GW Nam Thuen2 hydropower project in Lao PDR, which benefited from$91 million in MIGA political risk insurance and $50 millionin an IDA partial risk guarantee. <strong>The</strong>se guarantees were essentialfor the participation <strong>of</strong> private lenders in the $1 billionloan consortium, which also included public agencies.Is there scope for greatly expanded use <strong>of</strong> the <strong>World</strong> <strong>Bank</strong>’spartial risk guarantees or MIGA’s political risk insurancein promoting renewable energy? IEG’s evaluation <strong>of</strong> WBGguarantees found that guarantees had been underutilizedand that high processing and transaction costs and—inMIGA’s case—eligibility restrictions on the type <strong>of</strong> risks thatcan be covered limited the WBG’s ability to expand guarantees.With a change in the MIGA Convention, MIGA’scoverage is now expanded, but its institutional constraintswould still need to be overcome.For the <strong>World</strong> <strong>Bank</strong>, supporting national guarantee facilitiesis one approach. 10 <strong>The</strong> <strong>World</strong> <strong>Bank</strong> could, for instance,help countries assess the fiscally prudent opportunities forfeed-in tariffs or renewable portfolio standards and supportguarantees for countries with sustainable plans.Guarantees have benefits, but add to the cost <strong>of</strong> finance.It may be possible to use carbon finance to <strong>of</strong>fset some<strong>of</strong> this cost. As noted, at current carbon prices, annualrevenues from carbon credit sales provides little helpwith debt finance and little impetus for investment. Muchgreater leverage could be achieved, however, if carbonsales revenue were used to finance guarantee or insurancepayments, which in turn permitted lenders to <strong>of</strong>fer longerloan durations.Promote renewable energy -friendly pricing regulationA renewable energy plant’s ROE is very sensitive to pricing<strong>of</strong> power. Appendix figure A.3 shows the ROE for three differentplants, evaluated at a range <strong>of</strong> different tariffs. As inthe case <strong>of</strong> carbon revenue, higher tariffs have a bigger effecton plants with higher capacity utilization, other thingsbeing equal. Under the assumptions shown, wind doesnot become commercially attractive until tariffs exceed10 cents/kWh.<strong>The</strong> returns to a renewable energy plant arevery sensitive to power tariffs.Countries have purely domestic rationales for paying a premiumfor renewable energy, including local pollution reduction,insurance against fuel price shocks (Hertzmark 2007),22 | Climate Change and the <strong>World</strong> <strong>Bank</strong> Group

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!