During maintenance, it is essential that the equipment is isolated and earthed. One of theessential requirements of earthing is that earthing must be actually visible from the pointof working in the substation. Where this is not possible, provision of temporary earthingis made near the equipment. Besides the permanent illumination, provision should also bemade <strong>for</strong> portable lights <strong>for</strong> which purpose power outlets should be provided inmarshalling boxes or equipment cubicles.1-19