EDC PR 2016 (FS section)
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Financial Statement<br />
During the relocation and construction of the Nasulo Power Plant, the Company incurred general<br />
borrowings used to fund the project. In 2014, the borrowing costs capitalized in connection with<br />
the project amounted to ₱14.4 million with capitalization rate of 6.3% per annum.<br />
The Company performed testing run from April 2014 to July 20, 2014. The total revenue<br />
generated from testing amounted to ₱343.5 million. Out of this amount, ₱99.8 million was offset<br />
against the costs of testing whether the assets are functioning properly.<br />
On July 21, 2014, the Parent Company declared that the Nasulo Power Plant, after achieving a<br />
capacity of 49.4 MW, was already complete and in the condition necessary for it to operate as<br />
intended by management. Consequently, the total cost of the newly constructed assets was<br />
reclassified from “Construction in progress” to “Power Plants” category. Upon completion of the<br />
Nasulo Power Plant, the adjacent Nasuji Power Plant with capacity of 20 MW has been placed on<br />
preservation mode.<br />
In light of the completion of the Nasulo Power Plant, the Parent Company has determined that the<br />
impairment loss previously recognized on assets transferred to and installed in Nasulo (from<br />
NNGP) must be reversed as the service potential of those assets has now been established.<br />
Accordingly, reversal of impairment loss amounting to ₱2,051.9 million was recognized in 2014<br />
representing the net book value of assets installed in Nasulo Power Plant had there been no<br />
impairment loss previously recognized on these assets. The corresponding deferred tax asset<br />
amounting to ₱205.2 million has likewise been reversed. No similar reversal was recognized in<br />
<strong>2016</strong> and 2015.<br />
From originally being part of the NNGP CGU, the related assets have now become part of the<br />
CGU consisting of Nasulo/Nasuji steam field and power plants. The recoverable amount of such<br />
CGU as of July 31, 2014, the effective date of the reversal, determined by the Parent Company is<br />
estimated to be at ₱15,673.6 million, representing the value in use computed using 8.7% pre-tax<br />
discount rate. The amount of reversal of impairment was presented under NIGBU operating<br />
segment since the CGU is located in Negros Island (see Note 5).<br />
Completion of the Rehabilitation of Bac-Man Geothermal Power Plants (BMGPP)<br />
On May 5, 2010, BGI acquired the BMGPP in an auction conducted by PSALM where BGI<br />
submitted the highest offer price of US$28.3 million.<br />
Located in Bacon, Sorsogon City and Manito, Albay in the Bicol region, the BMGPP package<br />
consists of two steam field complexes. The Bac-Man I power plant has two 55-MW generating<br />
units (Unit 1 and Unit 2), while Bac-Man II power plant has one 20-MW generating units (Unit 3).<br />
<strong>EDC</strong> supplies the steam that fuels these power plants.<br />
Units 1, 2 and 3 became available for use on January 28, 2014, June 3, 2014 and October 1, 2013,<br />
respectively. Total borrowing costs capitalized to the project amounted to ₱9.5 million in 2014<br />
from general borrowings using a capitalization rate of 6.5% per annum. The total cost reclassified<br />
from construction in progress to power plant account amounted to ₱1,574.4 million,<br />
₱2,178.7 million and ₱551.3 million for Units 1, 2 and 3, respectively.<br />
In October 2014, the turbine retrofitting for Bac-Man Unit 2 was completed, increasing its<br />
capacity to 60 MW. Similarly, on February 20, 2015, the Company completed the installation of<br />
the brand new Toshiba steam turbine rotor unit and diaphragms for its Unit 1, increasing its<br />
capacity to 60 MW.<br />
229