FINAL<br />

1 2 3 4 5 6 7 10 13 16 17 18 21 22 23 24<br />

Wastewater Capital Program - Preferred <strong>Regional</strong> Servicing Strategy<br />

Region<br />

Capital Plan<br />

Project No.<br />

Area Project<br />

ID<br />

Combined<br />

Project<br />

Delivery<br />

Implementation<br />

Order<br />

Project Description<br />

System<br />

HW<br />

Project<br />

Type<br />

Project<br />

Type<br />

Diameter<br />

(mm)<br />

Length (m), Flow<br />

(L/s), Volume<br />

(m 3 )<br />

Unit Rate<br />

$/m, $/Lps, $/m 3<br />

Base Cost<br />

$M (2012)<br />

Other Costs<br />

(Crossings<br />

etc.)<br />

$M (2012)<br />

Total Cost<br />

$M (2012)<br />

Year<br />

Req'd<br />

Period Req'd<br />

Growth Areas<br />

Serviced<br />

Comment<br />

Central 1 AT1 AT5 3 Upgrade Aerotech Drive Pumping station to 145 L/s, from 15 L/s (130 L/s upgrade) Aerotech WW - Str WWPS-U N/A 130 $6,000 $0.78 $0.00 $1.25 2031 2031-2036 Aerotech Employment growth. Development of 121 Ha.<br />

Central 2 AT2 AT4 1 Upgrade WWTF to service employment growth flows Aerotech WW - TF WWTF-U N/A 7.65 MLD N/A $13.60 $0.00 $21.76 2031 2031-2036 Aerotech Employment growth. Development of 121 Ha.<br />

Central 3 AT3 5 Upgrade sewer conveyance to WWTF, from Aerotech Drive PS to WWTF Aerotech WW - CS WWM 450 mm 1,650 $895 $1.48 $0.00 $2.36 2031 2031-2036 Aerotech Employment growth. Development of 121 Ha.<br />

Central 4 AT4 AT2 2 Re-locate treated effluent discharge location to Soldiers Lake Aerotech WW - CS WWM 450 mm 6,346 $895 $5.68 $5.11 $17.26 2031 2031-2036 Aerotech Employment growth. Development of 121 Ha.<br />

Central 5 AT5 AT1 4 Upgrade Aerotech Drive PS forcemain to 145 L/s, from 15 L/s (130 L/s upgrade) Aerotech WW - FM WWFM 350 mm 268 $1,193 $0.32 $0.00 $0.51 2031 2031-2036 Aerotech Employment growth. Development of 121 Ha.<br />

West 27 BL1 BL2 2 450 mm WWFM from BLT PS to 125 m south of Governors Lake Dr BLT WW - FM WWFM 450 mm 2290 $1,629 $3.73 $1.25 $7.97 2021 2021-2026 28<br />

West 28 BL2 BL1 1 New BLT PS WWPS at Timberlea Village Pky (Site to be confirmed) WWPS BLT WW - Str WWPS-N 220 $6,000 $1.32 $0.00 $2.11 2024 2021-2026 28, 51<br />

Ongoing study being completed by Dillon Consulting - 1 road<br />

crossing (probably opencut)<br />

West 29 BL3 BL5 4 New wastewater pumping station at Church St WWPS (Exact site to be determined) BLT WW - Str WWPS-N 220 $6,000 $1.32 $0.00 $2.11 2021 2021-2026 28, 51<br />

West 30 BL4 3 600 mm WWM from Governor Lake Drive to Church St PS BLT WW - CS WWM 600 mm 1,124 $1,060 $1.19 $0.00 $1.91 2024 2021-2026 28, 51 3 minor creek crossings and 1 road (TBC)<br />

West 31 BL5 BL3 5 450 mm WWFM from Church St PS to upstream of Bayers Lake PS BLT WW - FM WWFM 450 mm 2,831 $1,629 $4.61 $0.51 $8.20 2024 2021-2026 28, 51 1 hwy ramp crossing<br />

West 31 BL6 9<br />

600 mm Hwy 3 WWM from RAMP SSH-4 to Bicentennial Hwy and North West Arm<br />

Dr<br />

BLT WW - CS WWM 600 mm 783 $1,060 $0.83 $0.00 $1.33 2024 2021-2026 28, 51<br />

West 55 BL7 7 Upgrade Bayers lake PS BLT WW - Str WWPS-U 220 $6,000 $1.32 $0.00 $2.11 2024 2021-2026 28, 51<br />

West 57 BL8 8 450mm WWFM from Bayers Lake PS BLT WW - FM WWFM 450 mm 810 $1,629 $1.32 $2.11 2024 2021-2026 28, 51<br />

West 56 BL9 6 600mm WWM to Bayers lake PS BLT WW - CS WWM 600 mm 513 $1,060 $0.54 $0.87 2024 2021-2026 28, 51<br />

East 38 DA1 1 Gravity sewer from Little Albro Lake to Jamieson St PS Dartmouth SW - Pipe SWM 450 mm 2,207 $895 $1.98 $0.38 $3.76 2013 2012-2016 to remove albro lake input<br />

East 39 DA2 2<br />

450mm surface water sewer from Fenwick St to Old Ferry Rd PS with the addition of<br />

Maynard St<br />

Dartmouth SW - Pipe SWM 450 mm 1,681 $895 $1.50 $0.38 $3.01 2014 2012-2016 to remove maynard lake input<br />

East 40 DA3 4 Sewer twinning along existing roads - Albro Lake/Slayter St to Ferry St PS Dartmouth WW - TS WWM 750 mm 3,370 $1,439 $4.85 $1.08 $9.48 2016 2016-2021 3, 4, 5, 6, 13, 15, 16<br />

East 41 DA4 8 Storage at Shannon Park vicinity Dartmouth WW - Str SF-N 6,800 $2,000 $13.60 $0.80 $23.04 2031 2031-2036<br />

East 42 DA5 9 Storage at Anderson Lake vicinity Dartmouth WW - Str SF-N 5,500 $2,000 $11.00 $0.80 $18.88 2039 2036-2041 48<br />

1, 2, 7, 48, 49, 50<br />

East 43 DA6 DA7 5<br />

Upgrade of Ferry Rd PS by 807 L/s to provide total capacity of 900 L/s (existing PS<br />

has 93 L/s)<br />

Dartmouth WW - Str WWPS-U 807 $7,500 $6.05 $0.00 $9.68 2019 2016-2021 3, 4, 5, 6, 13, 15, 16<br />

East 44 DA7 DA6 6 825mm Ø Ferry Rd forcemain for 900l/s Dartmouth WW - FM WWFM 825 mm 657 $2,695 $1.77 $0.00 $2.83 2019 2016-2021 3, 4, 5, 6, 13, 15, 16<br />

East 45 DA8 7 Upgrade of Dartmouth WWTF Dartmouth WW - TF WWTF-U 16.06 MLD N/A $24.50 $0.00 $39.20 2021 2021-2026<br />

East 46 DA9 3 I/I Reduction Program Dartmouth I/I $2.00 $0.00 $3.20 2015 2012-2016<br />

East 47 EP1 1 I/I Reduction within Eastern Passage Drainage Area Eastern Passage I/I $1.30 $0.00 $2.08 2014 2012-2016 Unknown<br />

East 48 EP2 8<br />

Upgrade of Eastern Passage WWTF.<br />

EP WWTF is currently being upgraded and expanded with allocation for growth<br />

considered. Projects to reduce I/I are proposed. Actual growth is to be monitored to<br />

confirm impacts on infrastructure<br />

Eastern Passage N/A $0.00 $0.00 $0.00 10, 12, 18<br />

East 49 EP3 6 Storage Tank at Bissett Lake-Attwood PS Eastern Passage WW - Str SF-U N/A 1,150 $2,000 $2.30 $0.00 $3.68 2029 2026-2031 18<br />

East 50 EP4 2 Upgrade Quigley's Corner Pumping Station Eastern Passage WW - Str WWPS-U 10 $6,000 $0.06 $0.00 $0.10 2014 2012-2016 12<br />

East 51 EP5 7 Twinning of existing Pressure Sewer from Caldwell to terminus Eastern Passage WW - CS WWM 675 mm 7,058 $1,312 $9.26 $1.35 $16.98 2036 2031-2036 10, 18<br />

East 52 EP6 EP7, EP8 3 Local pipe upgrades throughout system Eastern Passage WW - CS WWM 300 mm 1,554 $783 $1.22 $0.00 $1.95 2026 2026-2031<br />

East 53 EP7 EP6, EP8 4 Local pipe upgrades throughout system Eastern Passage WW - CS WWM 450 mm 5,477 $895 $4.90 $0.00 $7.84 2026 2026-2031<br />

East 54 EP8 EP6, EP7 5 Local pipe upgrades throughout system Eastern Passage WW - CS WWM 600 mm 896 $1,060 $0.95 $0.00 $1.52 2026 2026-2031<br />

West 19 HA1 HA2 7 Upgrade of Kearney Rd PS <strong>Halifax</strong> WW - Str WWPS-U N/A 920 $7,500 $6.90 $0.00 $11.04 2021 2021-2026 25, 37, 46 Upgrade of Kearney Rd PS<br />

West 20 HA2 HA1 8 900 mm WWFM from Kearney Rd PS to Bicentennial Hwy (Hill top) <strong>Halifax</strong> WW - FM WWFM 900 mm 4,708 $2,065 $9.72 $2.55 $19.63 2021 2016-2021 25, 37, 46<br />

West 21 HA3 3 900 mm WWM from Bicentennial Hwy (Hill top) to St Margarets Bay Rd <strong>Halifax</strong> WW - TS WWM 900 mm 2,701 $1,796 $4.85 $5.03 $15.81 2021 2016-2021 23, 24, 25, 27, 28, 37, 46, 51<br />

West 22 HA4 2 Gravity sewer from St Margarets Bay Rd to Armdale Rd PS <strong>Halifax</strong> WW - TS WWM 900 mm 1,597 $1,796 $2.87 $0.95 $6.11 2019 2016-2021 23, 24, 25, 27, 28, 37, 46, 51<br />

Based on the Eastern Passage Management Study (CBCL, 2006)<br />

that indicates that I/I reduction in the order of 1100 L/s is feasible<br />

at a cost of $1.3M<br />

Current upgrade being implemented. Capacity of upgraded facility<br />

25MLD (ADF), 75MLD (PWWF). See Appendix L: XCG WWTF<br />

Capacity Memo - no expansion required.<br />

Upgrade of Quigley's Corner PS of 10 L/s to maintain baseline<br />

<strong>volume</strong> of overflows<br />

Local pipe (300mm) upgrades to address existing conveyance<br />

limitations<br />

Local pipe (450mm) upgrades to address existing conveyance<br />

limitations<br />

Local pipe (600mm) upgrades to address existing conveyance<br />

limitations<br />

3 minor creek crossings, 1 minor road crossing and 1 major road<br />

crossing<br />

1 minor creek crossing, 5 minor road crossings, and 1 major road<br />

crossing<br />

1 minor creek crossing, 1 road crossing (Keating Rd - Probable<br />

opencut)<br />

West 23 HA5 HA6 4 Upgrade of Armdale (Rotary) Rd PS <strong>Halifax</strong> WW - Str WWPS-U N/A 1,420 $9,000 $12.78 $0.00 $20.45 2021 2021-2026 23, 24, 25, 27, 28, 37, 46 Upgrade of Armdale (Rotary) Rd PS<br />

West 24 HA6 HA5 5 Forcemain from Armdale PS to Punch Bowl Dr (Hill Top) <strong>Halifax</strong> WW - FM WWFM 1050 mm 2,299 $3,379 $7.77 $6.62 $23.02 2021 2021-2026 23, 24, 25, 27, 28, 37, 46, 51 8 road crossings (Probable opencut)<br />

West 25 HA7 6 Gravity sewer from hill top to Herring Cove diversion <strong>Halifax</strong> WW - TS WWM 1050 mm 989 $2,941 $2.91 $2.95 $9.38 2021 2021-2026<br />

West 26 HA8 1 I/I Reduction Program <strong>Halifax</strong> I/I $4.00 $0.00 $6.40 2013 2012-2016 25, 37, 46<br />

23, 24, 25, 27, 28, 29, 31, 37,<br />

46, 51<br />

4 road crossings (Probable opencut)<br />

Kearney Lake Rd, Flamingo, Bayers Lake, Seton Rd, Dutch<br />

Village Rd. Would benefit north end of peninsula but not<br />

considered a complete solution.<br />

October 31 2012 Page 176 of 272<br />

2012-09-25-RWWFP Preliminary Capital Program - FINALv3.xlsxCapital Program