E. Cost Estimates of Alternative Systems Costs - Construction cost estimates for the<br />

alternative water and sewer systems evaluated in the study were broken down into two<br />

separate components. The first component included the construction costs for water<br />

distribution and wastewater collection systems within the <strong>Four</strong> <strong>Corner</strong>s planning area. The<br />

configurations ofthese systems were dictated by the physical locations of water supply and<br />

wastewater treatment in addition to regulatory requirements. The second component<br />

involves the construction costs for the water supply plant and the wastewater treatment plant<br />

which are based upon the cost of new facility construction or in the case of existing plant<br />

availability, the capital recovery costs of the facilities already constructed. All construction<br />

cost estimates are based upon current unit costs for projects similar to scope and size of<br />

those evaluated in the study.<br />

The Alternative System Cost Table provides a summary of the construction costs for the<br />

water supply, wastewater treatment, water distribution and wastewater collection systems<br />

alternatives. Detailed cost construction costs estimates for water distribution and wastewater<br />

collection systems evaluated are included in the appendices of this report.<br />

Page 22 of28<br />

Preliminary Engineerng Report