6.1 WATER AND WASTEWATER SYSTEM LAYOUT<br />

With the exception of the points of source connection for water supply and wastewater<br />

treatment, there is very little difference in the overall water and sewer system layouts for<br />

the three scenarios evaluated (On-site, Kingsbridge MUD and North Mission Glen<br />

MUD). Due to the size of the planning area, pump stations and lift stations are necessary<br />

for an efficient wastewater collection system for each of the scenarios evaluated.<br />

Section 6.2 discusses the recommended source of water supply and wastewater treatment<br />

as the Kingsbridge MUD option. As shown in the water distribution system layouts and<br />

wastewater collection system layouts in Appendix A, the <strong>Four</strong> <strong>Corner</strong>s Planning Area<br />

was broken down into three geographic service areas. These areas account for the<br />

majority of the existing 350 connections. The detailed cost estimates provided in<br />

Appendix A for this scenario include a breakdown of water distribution and wastewater<br />

collection system costs by each individual area. Table 6.1.1 provides a summary of the<br />

water distribution and wastewater collection system costs for the Kingsbridge MUD<br />

option.<br />

<strong>Four</strong> <strong>Corner</strong>s Area <strong>Water</strong> and Wastewater Facilities Planning Study<br />

FINAL REPORT<br />

Revised 2/10/99<br />

Page 6-1