COST SUMMARY<br />

WATER DISTRIBUTION &<br />

WASTEWATER COLLECTION SYSTEMS<br />

KINGSBRIDGE MUD OPTION<br />

SERVICE SERVICE SERVICE<br />

AREA 1 AREA2 AREA3<br />

WASTEWATER COLLECTION SYSTEM<br />

Construction $2,237,015 $ 449,260 $ 640,280<br />

Contingencies (15%) 335,550 67,390 96,040<br />

Engineering (13%) 334,440 67,160 95,720<br />

Administration (5%) 145,350 29,190 41,600<br />

Total Cost $3,052,355 $ 613,000 $ 873,640<br />

WATER DISTRIBUTION SYSTEM<br />

Construction $1,580,340 $ 322,130 $ 269,330<br />

Contingencies (15%) 237,050 48,320 40,400<br />

Engineering (13%) 236,260 48,160 40,260<br />

Administration (5%) $ 102,680 $ 20,930 $ 17,500<br />

Total Cost $2,156,330 $ 439,540 $ 367,490<br />

TOTAL WATER DISTRIBUTION<br />

& WASTEWATER COLLECTION $5,208,685 $ 1,052,540 $ 1,241,130<br />

TOTAL AREA<br />

OUR CORNER<br />

$ 3,326,555<br />

498,980<br />

497,320<br />

216,140<br />

$ 4,538,995<br />

$ 2,171,800<br />

325,770<br />

324,680<br />

$ 141,110<br />

$ 2,963,360<br />

$ 7,502,355<br />

Total construction cost for the water distribution and wastewater collection system to<br />

serve the 350 existing connections in the planning area is $7,502,355. If phasing of the<br />

overall water and sewer system is required to meet available funding sources, the three<br />

service areas shown in the cost estimate provide a geographic breakdown for<br />

implementation. Implementation of water and sewer service in areas one and two would<br />

provide utility service to approximately 200 of the existing 350 connections.<br />

B. Project <strong>Water</strong> Supply And Wastewater Treatment Plant Requirements - The<br />

average daily water demand for the existing 350 connections is 138,000 gallons per day<br />

(gpd) while the average daily wastewater flows is 115,000 gpd. The adjacent district,<br />

Kingsbridge MUD currently has surplus wastewater capacity available and will have<br />

water supply capacity available in the near term.<br />

Preliminary £"'ngineering Report<br />