- Page 2 and 3:
Vision To be among the leading c
- Page 4 and 5:
CONTENTS SUPPLY APPLICATION 1.0 Ten
- Page 6 and 7:
1.0 TENAGA NASIONAL BERHAD ELECTRIC
- Page 8 and 9:
e) Elektrik Bestari TNB provides el
- Page 10 and 11:
1.10 Types Of Supply Application Al
- Page 12 and 13:
1.18 Tariff Please refer to the Tar
- Page 14 and 15:
2.4 TNB Supply Lead Time The flowch
- Page 16 and 17:
Stage Description 2 TNB Register Ap
- Page 18 and 19:
Steps Action Reference 2 After appr
- Page 20 and 21:
Steps 7 8 Action Advise applicant t
- Page 22 and 23:
CONTENTS Page 1.0 PLANNING FOR C
- Page 24 and 25:
1.1.1.1 Technical Requirements For
- Page 26 and 27:
Should a preliminary examination of
- Page 28 and 29:
• Capacitance connected in parall
- Page 30 and 31:
SECTION 2.0 PLANNING AND DESIGN CRI
- Page 32 and 33:
For the purpose of this guideline,
- Page 34 and 35:
Table 2.3.4.1: Voltage limits on sw
- Page 36 and 37:
2.3.5.6 If under the operating cond
- Page 38 and 39:
Table X: Planning Levels for Harmon
- Page 40 and 41:
3) At the terminals of a Customer
- Page 42 and 43:
2.5.3 Protection System Evaluation
- Page 44 and 45:
3.2 Group Diversity Group diversity
- Page 46 and 47:
- 132/33kV, 2 x 90 MVA - 132/22kV,
- Page 48 and 49:
The establishment of transmission m
- Page 50 and 51:
CONTENTS Page ABBREVIATIONS .......
- Page 52 and 53:
1.0 GENERAL REQUIREMENTS 1.1 All th
- Page 54 and 55:
ii. iii. iv. The tickness of board
- Page 56 and 57:
4.0 GROUP METERING FOR WHOLE CURREN
- Page 58 and 59:
v. The panel cover and metal plate
- Page 60 and 61:
6.2 Specifications For Metering PTs
- Page 62 and 63: 6.7.2 Outdoor Breakers A ‘marshal
- Page 64 and 65: GLOSSARY AND DEFINITIONS In this gu
- Page 66 and 67: Embedded Generating Unit A generati
- Page 68 and 69: Protection Protection Apparatus Pro
- Page 70 and 71: Appendix Topic Page 1 List of Kedai
- Page 72 and 73: Appendix 1 List of Kedai Tenaga in
- Page 74 and 75: Appendix 1 List of Kedai Tenaga in
- Page 76 and 77: Appendix 3 PERMOHONAN BEKALAN ELEKT
- Page 78 and 79: Appendix 5 TENAGA NASIONAL B E R H
- Page 80 and 81: Appendix 7 PART B : TNB SUPPLY APPL
- Page 82 and 83: Appendix 9 JOINT MEETING ACTION LOG
- Page 84 and 85: Appendix 11 SAMPLE OF APPOINTMENT L
- Page 86 and 87: Appendix 12 Load Category Total lig
- Page 88 and 89: Appendix 13 LOCATION PLAN TENAGA NA
- Page 90 and 91: Aku Janji dan Tanggungrugi *Pemilik
- Page 92 and 93: Appendix 16 Demand forecast and sub
- Page 94 and 95: Appendix 17 SUBSTATION LAYOUT DRAWI
- Page 96 and 97: Appendix 18 SITE PLAN / LOCATION PL
- Page 98 and 99: Appendix 18 LOGO DETAIL FOR DOUBLE
- Page 100 and 101: Appendix 19 (Drawing 7B) MV/HV, 1 O
- Page 102 and 103: Appendix 19 (Drawing 7D) 3 FEEDER M
- Page 104 and 105: Appendix 19 (Drawing 7F) MV/HV, 3 F
- Page 106 and 107: Appendix 19 (Drawing 7H) 1, 2, 3 OR
- Page 108 and 109: Appendix 19 (Drawing 7J) 1, 2, 3 OR
- Page 110 and 111: Appendix 20 TENAGA NASIONAL B E R H
- Page 114 and 115: Appendix 23 DRAWING NO 3A : OUTDOOR
- Page 116 and 117: Appendix 25 DRAWING NO 4A : 3 PHASE
- Page 118 and 119: Appendix 25 DRAWING NO 4C : 3 PHASE
- Page 120 and 121: Appendix 26 DRAWING NO. 4E TENAGA N
- Page 122 and 123: Appendix 27 DRAWING NO 5A : SINGLE
- Page 124 and 125: Appendix 27 DRAWING NO 5C : SINGLE
- Page 126 and 127: Appendix 28 DRAWING NO 5E: 3 PHASE
- Page 128 and 129: Appendix 29 TENAGA NASIONAL B E R H