2.0 SUPPLY APPLICATION FOR LOAD UP TO 100kVA<br />
2.1 Purpose<br />
The application for the supply of electricity with load up to 100kVA which is for a 3 phase low voltage system<br />
is outlined here.<br />
2.2 What The Applicant Should Do<br />
The applicant should take the following steps to apply for supply of electricity up to 100kVA for a 3-phase<br />
low voltage system.<br />
Steps Action Reference<br />
1<br />
Appoint an Electrical Contractor who is registered with The Energy<br />
Commission, who will act on their behalf and submit the application for the<br />
applicant using the Supply Application Form available at Kedai <strong>Tenaga</strong>.<br />
The Electrical Contractor must be<br />
registered with the Energy Commission<br />
2 Settle connection charges billed by TNB through the Electrical Contractor<br />
Statement of Connection Charges<br />
booklet available at any Kedai <strong>Tenaga</strong><br />
3<br />
After completion of TNB’s work (before installation of meter), the<br />
applicant shall:<br />
• Deposit a sum of money equivalent to 2 months bill or as reviewed from<br />
time to time. For deposit of more than RM2,000, the applicant can settle<br />
either in cash or Bankers Guarantee<br />
• Sign electricity supply contract with TNB through the appointed<br />
Electrical Contractor<br />
Tariff booklet available at the nearest<br />
Kedai <strong>Tenaga</strong><br />
2.3 What The Electrical Contractor Should Do<br />
The Electrical Contractor appointed by the applicant should take the following action:<br />
Steps Action Reference<br />
1 Submit application for the applicant using the Supply Application Form<br />
available at Kedai <strong>Tenaga</strong>.<br />
All documents in checklist must be completed, duly endorsed by the<br />
appropriate competent person(s) of the appropriate category and attached<br />
with the application.<br />
Appendix 3<br />
2 After TNB has :<br />
• validated compliance to checklist<br />
• conducted analysis of supply connection<br />
• reviewed connection charges and issue bill to contractor<br />
Statement of Connection<br />
Charges Booklet available<br />
at any Kedai <strong>Tenaga</strong><br />
The applicant shall settle connection charges to TNB.<br />
3 After TNB has implemented work on site, the Electrical Contractor shall:<br />
• Submit G and H form certifying the internal installations<br />
have been tested<br />
• Arrange for applicant to sign supply contract with TNB<br />
• Arrange appointment for meter installation with TNB<br />
Tariff Booklet available at nearest<br />
Kedai <strong>Tenaga</strong><br />