4.0 Application Process for Streetlight<br />
4.1 Purpose<br />
This procedure outlines the process for the application for streetlight.<br />
4.2 Types of Applications<br />
The three () types of application for streetlights are:<br />
• Application made by the local authority/government authority<br />
• Application by developer<br />
• Application by individual<br />
4.3 Application by Developer<br />
The local authority or developer should take the following steps to apply for streetlight.<br />
Steps<br />
Action<br />
1 Appoint a Consultant Engineer and an Electrical Contractor that is registered with the Energy<br />
Commission.<br />
2 The application is made together with the supply application for a new housing development with<br />
all the load details of the proposed public lighting that is approved by the local authority.<br />
4.4 Application By Individuals/Local Authority/Government Authority<br />
The application process is similar for both individuals and local authority or government authority. Individuals<br />
must already have an account with TNB. The installation of streetlight depends on:<br />
• Installation of streetlight on existing TNB pole<br />
• Installation involving additional poles<br />
IF<br />
Installation of streetlight on existing<br />
TNB pole<br />
Installation involving<br />
additional poles<br />
THEN<br />
Consumer submits application to the Kedai <strong>Tenaga</strong>.<br />
The applicant settles the full cost of additional new pole/poles<br />
installed.<br />