2.3.6. .2 A Consumer who intends to connect non-linear loads to the TNB system shall carry out assessment harmonic<br />
distortion levels for the connection of each non-linear Load to the Distribution System. TNB will verify the<br />
results of the assessments.<br />
2.3.6. Consumers shall ensure that the Immunity Level of their plant and Apparatus is compatible with the<br />
electromagnetic disturbances present on the System including harmonics.<br />
2.3.6. .4 In assessing the level of harmonic distortion and individual harmonic levels at the planning stage, the assessment<br />
will be carried out at a realistic system operating condition giving the minimum number of connections with<br />
which that point on the system can be operated within normal voltage limits and following secured contingency<br />
events. This condition shall be considered as representative of the type of system conditions under which the<br />
harmonic distortion and individual harmonic levels will be at their highest level.<br />
2.3.6.5.5 If under the operating conditions describes in ..6. 2.3.6.1 (a) (a) the harmonic distortion and individual harmonic levels<br />
due to the load exceed the limits then harmonic filters which will reduce the harmonics to an acceptable level<br />
shall be installed to bring the levels within limits. The system overall performance yardstick for the level of<br />
harmonic reduction to be achieved shall be based upon enabling connection of other similar harmonic producing<br />
load and/or permitting for future extension and development of the location with further harmonic producing<br />
load installations.<br />
2.3.6.6.6 The planning limits of harmonics that are acceptable of the distribution system are in accordance with MS<br />
IEC 61000-3-6 “ Assessment of emission limits for distorting loads in MV & HV power systems”, and where<br />
appropriate Engineering Recommendations G5/4 is adopted.<br />
2.3.6.7.7 TNB uses the procedures contained in this document to plan the connection of loads producing harmonics and<br />
applies the limits therein in measuring and monitoring the levels of harmonics at such points of connection.<br />
These are given in summary in the tables below.<br />
36 TENAGA<br />
NASIONAL B E R H A D