MWRI and IRG met on November 1 to discuss the Year 4 Work Plan comments. Dr. Khaled, Eng.<br />

Nabila, Mr. Andy, Eng. Nabil, and Dr. Wadie attended the meeting.<br />

MWRI (MIC) and IRG held a second meeting on November 13 to discuss the status of MIC’s<br />

efforts to review the sample digital map. Progress was disappointing and led to concerns about the<br />

practicality of appointing MIC to undertake the digital map review. Mr. Andy, Dr. Hesham Mustafa,<br />

and Eng. Nabil attended the meeting.<br />

MWRI (CDIAS) and IRG met on November 14 to discuss the future cooperation between IWRM <strong>II</strong><br />

project and MWRI CDIAS during Year 3 Quarter 4 and Year 4. Mr. Andy, Eng. Nabil, Dr. Moamen,<br />

Eng. Nagwa, and Eng. Abeer attended the meeting. It was decided that CDIAS would observe the<br />

next Task 1.1 training to be given by the project and then implement the last course to be held in the<br />

first quarter of 2012.<br />

The head of the Irrigation Department issued decree No. 214 dated November 22, 2011 extending<br />

LOWP to Eng. Ayman Abd Elsalam Shedeed and Eng. Akmal Aziz Badie from November 14, 2011<br />

up to April 30, 2012 to work with consultant in Zagazig and Mansoura ROs respectively.<br />

The head of the Irrigation Department issued decree No. 213 dated November 22, 2011 granting<br />

Eng. Nabil Nassif Faragalla five months LOWP to work with the consultant as Water Resources<br />

Management Specialist. Eng. Nabil started his assignment on LWOP on November 23, 2011.<br />

MWRI (CDIAS) and IRG met on November 22 to discuss the procedure for involving the CDIAS<br />

in the ongoing Task 1.1 training courses, related to IWRM <strong>II</strong>, during Year 3 Quarter 4 and Year 4 in<br />

addition to IWRM I. Mr. Andy, Dr. Khaled, Eng. Nagwa, and Eng. Nabil attended the meeting.<br />

The Year 4 Work Plan workshop was held from November 16 to 18. The Steering Committee<br />

members, USAID representatives, minister’s office representatives, East Delta Region head of<br />

Central Directorates & General Directorates of Water Resources and Irrigation, IRG representatives<br />

and field Engineers from West Belbeis, Elmollak, Deyarb Negm, Elbohirat IWMDs and the head of<br />

Qena technical office of Central Directorate of Water Resources & Irrigation attended the workshop.<br />

The Year 4 Work Plan has been approved.<br />

A project staff meeting was held on December 7 to discuss status, issues, and constraints to progress<br />

and actions to overcome constraints. The entire technical staff from Cairo and both field offices<br />

attended. A summary of issues and constraints identified in the meeting was written and shared with<br />

the Project Coordinator.<br />

Mr. Tczap and Eng. Nabil met with Dr. Khaled, Project Coordinator, on December 8 to discuss the<br />

findings that came out of the December 7 project staff meeting.<br />

Giza Systems company, a local vendor of water monitoring equipment, made a presentation to the<br />

project on December 12 on the flow measurement equipment they provide. In addition to project<br />

staff, three members of the MRWI Telemetry staff and Eng. Abeer Salama attended.<br />

Mr. Tczap met with Eng. Wafaa, USAID COTR to discuss project status, budget realignment, and<br />

various other project activities.<br />

The project distributed the final versions of the Year 4 Work Plan and the Year 4 Workshop report<br />

on December 13.<br />

The project staff met with CDIAS on December 14. It had previously been decided that CDIAS<br />

would give the last remaining Task 1.1 training course and the meeting established the details and<br />

logistics of the upcoming course. The responsibilities of CDIAS and the project were clearly<br />

defined.<br />

Eng. Nagwa (CDIAS), Mr. Tczap, Eng. Nabil, Dr. Wadie, and Ms. Dahlia attended.<br />

6 ANNUAL REPORT YEAR 3 (JANUARY – DECEMBER 2011)