INTEGRATED WATER RESOURCE MANAGEMENT II - LIFE-IWRMII ...
INTEGRATED WATER RESOURCE MANAGEMENT II - LIFE-IWRMII ...
INTEGRATED WATER RESOURCE MANAGEMENT II - LIFE-IWRMII ...
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Directorate<br />
• The BCWUAs’ Participatory Water Management (PWM) implementation training course<br />
conducted seven events. Eng. Nagwa Elkhsshab and Eng. Ezzat Elshafey (CDIAS) attended<br />
the East Dakahlia event.<br />
• 45 of 45 Winter Seasonal Meetings were held with BCWUAs Chairpersons.<br />
• 622 of 622 BCWUAs Board meetings were held to assign board members PWM training and<br />
subsequent activities.<br />
• Water Advisory Team coordination meetings held (27 events)<br />
IWMDs<br />
MWRI<br />
Area (d)<br />
BCs<br />
Status of BCWUAs End of Year 3<br />
BCWUA<br />
Users<br />
BCWUAs<br />
Formed<br />
Elected<br />
Board<br />
Members<br />
&<br />
Decrees<br />
MOU<br />
Internal<br />
Reg.<br />
Needs<br />
Assessment<br />
Maint.<br />
Priorities<br />
Damietta 2 59,243 61 24,567 27 27 27 27 27 27 27 27<br />
Elsalam 4 221,130, 97 17,598 56 56 56 56 56 56 56 56<br />
E. Dakahlia 8 355,124 329 137,328 141 141 141 141 141 141 141 141<br />
S. Dakahlia 5 198,795 127 299,302 88 88 88 88 88 88 88 88<br />
Ismailia 6 302,500 61 20,864 51 51 51 51 51 51 51 51<br />
Salhia 7 457,558 99 201,951 82 82 82 82 82 82 82 82<br />
E. Sharkia 5 211,233 187 72,542 83 83 83 83 83 83 83 83<br />
Qualubia 8 357,748 259 530,200 94 94 94 94 94 94 94 94<br />
Total 45 2,163,331 1220 1,304,352 622 622 622 622 622 622 622 622<br />
ID<br />
Cards<br />
Action<br />
Plan<br />
Task 1.1 PMP Indicators and Targets<br />
Year 1 Year 2 Year 3<br />
Task Indicator Units Baseline Target Actual Target Actual Target Actual<br />
1.1 Formation and Development of Branch Canal Water Users’ Associations (BCWUAs)<br />
1.1.a Number of IWMDs with staffed Water<br />
Advisory Teams<br />
Number 0 45 45 45 45 45 45<br />
1.1.b Number of GDs with staffed Water<br />
Advisory Teams<br />
Number 0 8 8 8 8 8 8<br />
1.1.c Percent of planned BCWUAs<br />
established by ministerial decree<br />
Percent 0 50 0 100 100 100 100<br />
1.1.d Percent of BCWUAs with maintenance<br />
priorities and action plans<br />
Percent 0 0 0 50 0 100 100<br />
1.1.e Percent of BCWUAs monitoring and<br />
reporting on branch canal water Percent 0 0 0 50 0 25 25<br />
supply<br />
TASK 1.2: SUSTAINABLE LOCAL FINANCING FOR CANAL AND<br />
DRAIN MAINTENANCE<br />
Very little activity was ongoing in January when the USAID Mid-Term Evaluation was underway and<br />
this task was put on hold until recommendations of the Evaluation became known. The Evaluation<br />
recommended, and MWRI concurred, to cease activity on this task and the project complied.<br />
TASK 1.3: IMPROVEMENTS IN <strong>WATER</strong> PRODUCTIVITY AND<br />
EFFICIENCY<br />
Dr. Wadie Fahim Mankarious (LTTA Senior Organization/Institutional Development Specialist) is<br />
the IRG coordinator for this task. He is supported by several local consultants, including Dr. Ahmed<br />
ANNUAL REPORT YEAR 3 (JANUARY – DECEMBER 2011) 9