not be considered final. The project cannot utilize resources from the private sector to perform<br />
quality assurance on the maps due to restrictions on sharing data with IRG. Therefore, we have been<br />
discussing the possibility of using the Ministry Information Center for this. Workload and other<br />
considerations have made MICs response inadequate. The project will continue to search for a way<br />
to perform the needed quality assurance effort but no solution exists as of the writing of this report.<br />
TASK 2.4: CAPACITY BUILDING OF MWRI PERSONNEL<br />
The project will not meet the objectives of this Task due to issues that arose in the early stages of the<br />
project that were never overcome. Out of 50 MWRI personnel programmed for enrollment in the<br />
M.S. Program, only 36 were identified by MWRI to participate. Only 20 of the 36 were accepted by<br />
universities and have been enrolled in M.S. programs. Two of the 20 participants have graduated to<br />
date and the project will continue to support the remaining 18 that are still pursuing their degrees.<br />
MONITORING AND EVALUATION<br />
Data collection has been slower than expected due to delays in installing the relevant data bases. In<br />
some cases the accuracy of data in-hand is suspect (MISD, cropped area) and in other cases the data<br />
must be back-calculated. The project is focusing on improving the quantity and quality of the M&E<br />
data and reasonable results are expected when the final M&E report is issued.<br />
EDUCATION, COMMUNICATION, PUBLIC AWARENESS AND PARTICIPATION<br />
No problems or issues to report.<br />
TRAINING<br />
Because of summer water shortages and the need to have district staff in the field full time, MWRI<br />
requested all June, July and August 2011 training be postponed until September. In previous years,<br />
training was suspended for one month in summer and proceeded at a reduced pace in the other<br />
summer months. This postponement this year delayed implementation of certain components of the<br />
training program. IWRM <strong>II</strong> and MWRI are aware of this situation and accelerated the training<br />
program starting in September and the original program is close to being back on schedule. New<br />
training courses have been identified and will be conducted in Year 4 without detriment to the<br />
project schedule and outputs.<br />
PROCUREMENT<br />
Practically all the required commodities were procured in Years 1 & 2. Cost containment principles<br />
were put in place and the total cost to date has been significantly less than budgeted. It has been<br />
agreed to procure additional equipment for IWRM <strong>II</strong> directorates/districts with the remaining<br />
budget and also to procure replacement equipment for the IWRM I districts and directorates. This<br />
will required accelerated procurement to have everything purchased, delivered and installed prior<br />
to contract completion but no problem is foreseen in that regard.<br />