• Business Plan and Integrated Preventive Maintenance data sheets have been completed by all<br />
IWMDs. Review/revision of data was completed for all 45 IWMDs by the project.<br />
Compiling the data was completed for all IWMDs.<br />
• IRG staff visited Faraskour and Deyarb Negm IWMDs on 11 January and Toukh and Kafr<br />
Shoukr IWMDs on January16 for follow up and support as needed.<br />
• To provide follow-up support to <strong>LIFE</strong>/IWRM I, IRG staff, the Head of the Central<br />
Directorate for Maintenance (the head of the IWRM I & <strong>II</strong> M&E committee) and the Head<br />
of the Irrigation Sector Technical Office attended East & West Qena General Directorate’s<br />
monthly coordination meeting. They visited Armant, Esna, and Qena IWMDs and attended<br />
the Esna BCWUA’s summer seasonal meeting (January 25-27). Visits to Qous IWMD (E.<br />
Qena General Directorate) and Naga Hammadi IWMD (W. Qena General Directorate) were<br />
conducted and attended by Eng. Nabil Fawzi. IRG staff also attended West Sharkia and New<br />
Zefta General Directorate’s quarterly coordination meetings held during April & May<br />
respectively. The meetings were attended by the Irrigation and Drainage Undersecretaries,<br />
the General Directors, District Managers and Regional Advisor. IRG staff stopped making<br />
follow-up visits to the five IWRM I supported directorates at mid-year as directed by MWRI.<br />
• ADSL lines for internet access have been installed in all eight Directorate offices and 27 of<br />
45 IWMDs. A list of the 18 IWMDs lacking ADSL service was sent to the Project<br />
Coordinator for information and action. The continuation of this service requires payment of<br />
overdue telephone invoices and some of the districts do not have budget for this.<br />
• Directorate IT teams continued to make regular visits to their respective IWMDs to provide<br />
computer maintenance support.<br />
• Basic Management Skills training was conducted, 8 events.<br />
• IRG staff in ROs completed quarterly visits to the each of the 45 IWMDs two times (90<br />
trips) to evaluate their performance and provide technical support and advice.<br />
• Quarterly maintenance meetings were conducted and attended by project staff (5 events)<br />
• Advanced Computer Skills training course was completed. (7/7 events)<br />
• Directorate Under Secretary monthly meetings were held (60 events) attended by MWRI and<br />
MALR staffs. Dr. Khaled Toubar (MWRI Project Coordinator) and Eng. Nabil Fawzi<br />
attended some of these meetings.<br />
Task 2.2 PMP Indicators and Targets<br />
Year 1 Year 2 Year 3<br />
Task Indicator Units<br />
Baseline<br />
Target Actual Target Actual Target Actual<br />
2.2 Formation and Development of Integrated Water Management Districts (IWMDs)<br />
2.2.a Number of IWMDs established<br />
with fully staffed senior positions<br />
Number 0 45 45 45 45 45 45<br />
2.1.b Number of IWMDs with<br />
completed integrated<br />
Number 0 0 0 45 45 45 45<br />
maintenance plans<br />
2.2.c Number of IWMDs with a training<br />
room established and equipped<br />
Number 0 20 0 45 45 45 45<br />
2.2.d Number of general directorates<br />
with a computer training center Number 0 8 8 8 8 8 8<br />
established and equipped<br />
2.2.e Number of IWRM I IWMDs<br />
participating in coordination<br />
meetings<br />
Number 27 27 27 27 27 27 27<br />
14 ANNUAL REPORT YEAR 3 (JANUARY – DECEMBER 2011)