INTRODUCTION<br />

The tables following this page present a summary of the status of the project budgets based on actual<br />

invoices through October 28 with estimates for expenditures in November and December. It should<br />

be noted that IRG has submitted a proposed budget realignment to USAID/Egypt for approval.<br />

The budget realignment has not been approved by USAID to date and therefore this report<br />

continues to utilize the original budget breakdown which results in some items appearing to be<br />

overspent to a large degree. Once the realignment is agreed upon and approved, future financial<br />

reports will be based on the new reallocation of budget line items with no change in the total budget<br />

and the actual status of each line item will be more accurately reflected.<br />