<strong>Annual</strong> Research <strong>Report</strong> <strong>2011</strong>-<strong>2012</strong><br />

Project Title:<br />

Periodic sampling and chemical analysis of fuels used in<br />

power plants<br />

Department: Chemistry & Process<br />

Project Manager: F.Borhan azad<br />

Employer: Iran Energy Efficiency Organization (SABA) Project Code: CPCSB01<br />

Project Staffs: A.Zahiri, S. E. Samadi<br />

Project Summary:<br />

Fuel testing and controlling its quality is important in operation of power plants. At<br />

present in most of the country's power plants, natural gas is used as main fuel and heavy<br />

fuel or gas oil as alternative one. The efficiency of power plants is affected by various<br />

factors including fuel heat value and composition. Moreover, the chemical composition<br />

of the fuels around the country is not identical and depends on gas providing source.<br />

Therefore in order to study the fuel quality effect on power plant performance, it is<br />

necessary to test fuels in various periods of the year. In this project 21 power plant unit<br />

was selected in such a manner that the effects of various climatic condition and units<br />

lifetimes could be studied. Then fuel sampling and testing were performed during five<br />

periods of a year. Also the operational data of each unit was gathered. Then the unit<br />

efficiencies during fuel sampling periods were calculated and their variations were<br />

plotted. In the next step, the testing results and operational data were analyzed and the<br />

effect of various factors such as fuel chemical composition, operational parameters,<br />

power plant lifetime and locations,. on plants efficiencies were determined. At final<br />

step, the efficiencies of power plants were compared and recommendations for their<br />

improvements were offered.<br />

Project results:<br />

• Study of the power plants in the different seasons of the year and comparing<br />

them from the efficiency and fuel specification point of views<br />

• Determining the priority of the power plants for installation of online fuel<br />

sampling and chemical analysis system.<br />

• Preparing proposal for using weight and colorific counters instead of current<br />

volume counters in power plants in short-term and long-term planning<br />

respectively<br />

• Preparing proposal for periodic sampling and chemical analysis of fuel in power<br />

plants<br />

• Offering recommendations regarding improvement of gas fuel heaters, using<br />

duct burner in gas turbines, modification of gas pipe line, proper using of gas<br />

units in power generation, ….<br />