<strong>Annual</strong> Research <strong>Report</strong> <strong>2011</strong>-<strong>2012</strong><br />

Project Title:<br />

Reliability Evaluation and Anticipation in Yazd Transmission<br />

and Sub transmission Network To Reduce Notsupplied<br />

Energy<br />

Department: Power System Study<br />

Employer: Yazd Electric Regional Company<br />

Project Staff: H.Danaie, J.Abbasi, N.Moslemi<br />

Project Manager: D.Jalali<br />

Project Code:PSYBY01<br />

Project Summary:<br />

Continuation and qualified supplying electrical energy is the main goal of electric<br />

utilities. This goal can be accessed by Power system reliability study. This study usually<br />

is done in two main parts, reliability evaluation and reliability anticipation. Each of<br />

them can be done either in power system planning or in power system operation.<br />

This project is done for reliability study in the transmission and sub transmission<br />

network of Yazd Regional Electric Company (YREC). As said above, reliability study<br />

in transmission and sub transmission network has two main parts as reliability<br />

evaluation and reliability anticipation. In the first part, by gathering data for planned and<br />

unplanned outages in transmission and sub transmission network in the period of 2007<br />

to 2010, a database was prepared by these data for further process. In this way, many<br />

different types of reporting for different usages can be made and at last these data yield<br />

to the force outage rate ( ) and the repair time (r) for the different elements in power<br />

system.<br />

Reliability evaluation was done by extracting the reliability indices from the mentioned<br />

database and different reports formed by it<br />

Second part includes the reliability anticipation by the method of minimum cutset<br />

algorithm, a powerful method for this analysis. This analysis has the following results:<br />

• Power system energy not supplied<br />

• Reliability indices in output nodes (loads)<br />

• Sensitivity analysis to find the critical elements in the network which cause<br />

to reduce the reliability indices.<br />