<strong>Annual</strong> Research <strong>Report</strong> <strong>2011</strong>-<strong>2012</strong><br />

Project Title:<br />

Consulting services in insulation assessment of Damavand<br />

power plant units through analysis and interpretation of the<br />

partial discharge measurement results and report<br />

Department: Electrical machines<br />

Employer: Damavand electrical power Generation Company<br />

Project manager: S. Gouran<br />

Project code:CEMTV01<br />

Project staff: S. AminiValashani, A. Farshidnia, R. Sarafraz<br />

Project Summary:<br />

On-line partial discharge measurement of the stator winding insulation is one of the<br />

appropriate methods in fault diagnosis of the electrical generators insulation. Since this<br />

method is inexpensive, simple and nondestructive as well as enables to prepare useful<br />

information about generators insulation, it is suitable as a predictive fault diagnosis<br />

method. On the other hand, due to poor operating condition of electrical machines in<br />

power plants, because of the high contamination and different operating regimes, these<br />

machines, in the most cases, are subjected to insulation degradation and reducing the<br />

remaining life. The excessive degradation of insulation in electrical equipments,<br />

eventually, leads to electrical insulation fault and unexpected stop of the electrical<br />

motor or generator which can impose high cost in maintenance and lack of production.<br />

Nowadays, implementation of predictive operating and maintenance systems, which are<br />

on the basis of on-line monitoring and assessment of an equipment condition, has a key<br />

role in reducing the operating and maintenance cost along with increasing the system<br />

reliability. Accordingly, on-line monitoring of partial discharge in electrical equipments<br />

can help to decrease the cost of maintenance and lack of production using on-time<br />

diagnosis of different insulation defects.<br />

According to domestic production of the most of the electrical generators in Damavand<br />

power plant, its associate manager decided to prepare and installation of partial<br />

discharge measurement equipments. Since the interpretation of the measured data needs<br />

to high qualified personnel, it was decided to prepare a contract between NRI and<br />

Damavand power plant in order to cooperation between engineers of two companies in<br />

interpreting of PD measured data. The main objective of this contract was analyzing the<br />

PD measured data of 12 gas unit(s). After the primary coordination, the relevant units<br />

were tested every two months and the results were sent to NRI where the results were<br />

analyzed and a prepared report was sent to Damavand power plant. At the end of this<br />

process, six abstract and two detailed reports (were) sent to Damavand power plant.<br />