A307_SIB Rev.5 dtd: 20.06.2013 Page 6 of 21<br />

BPCL-KR<br />

Job: A307<br />

period plus Three months claim period & separate 5% Bank Guarantee towards Price Reduction<br />

Schedule due to delay in delivery valid till contractual delivery date (CDD) + Five and half Months).<br />

2.3 For Training<br />

2.3.1 At Site: 100% payment against final bill to be submitted by seller after completion of training duly<br />

certified by site-in-charge.<br />

2.3.2 At Supplier’s Works: 100% payment against final bill to be submitted by seller after completion of<br />

training.<br />

2.4 Annual Maintenance Contract<br />

100% payment shall be paid at the end of each quarter of the contractual year against quarterly<br />

progressive bills to be submitted by Seller duly certified by Site-in-Charge.<br />

2.5 Payment for PGTR / Per Diem Charges for Supervision of Erection, Testing &<br />

Commissioning<br />

2.5.1 100% Payment of Invoice amount through direct wire transfer as per normal banking channels on<br />

completion of supervision activity / PGTR upon submission of Invoice, Time Sheet duly certified by<br />

Site In-Charge at BPCL Site, legible copy of visa (showing date of entry and date of exit from India)<br />

and passport (showing Name and Nationality of the personnel). Payment shall be made after<br />

deducting Income Tax at applicable rate.<br />

2.5.2 Where erection/commissioning supervision, commissioning assistance is required from the vendor,<br />

penalty for non mobilization/delay in mobilization as per order shall also be specified in the<br />

specifications. The penalty shall generally be 1.5 times the per diem rate for each day of delay of<br />

reporting to site and shall be in addition to price reduction for delayed delivery.<br />

2.5.3 Wherever supervision is in the scope of MR, bidders shall provide additional BG of an amount equal<br />

to the per diem charges for the number of days considered for evaluation over and above 10%<br />

PBG to cover compensation for delay in mobilising the erection/ commissioning personnel. This BG<br />

will be released to the bidder upon the erection/ commissioning personnel reporting at site. This BG<br />

shall be furnish along with dispatch documents which shall be initially valid up to six months whixh<br />

shall be extended based on the request by BPCL.<br />

2.6 General<br />

2.6.1 No initial advance payment along with Order shall be made by the Owner against Supplies as well<br />

as Services (i.e. Transportation, Erection, Site Work, etc.). If a Supplier insists on the same, their<br />

Offer shall be rejected.<br />

2.6.2 All Bank Guarantee(s) shall be issued through any Indian Scheduled Bank or branch of an<br />

International Bank situated in India and registered with Reserve Bank of India as scheduled foreign<br />

Bank as per Pro-forma provided in RFQ documents. All Bank Guarantees will be directly to BPCL by<br />

the Bank.<br />

2.6.3 All bank charges and stamp duties payable outside India in connection with payments shall be borne<br />

by the Supplier. All bank charges and stamp duties payable in India shall be borne by BPCL except<br />

L/C Amendment charges for delays in delivery. Confirmation charges for Confirmed L/C shall be<br />

borne by Supplier.<br />

2.6.4 Billing schedule shall be submitted to <strong>EIL</strong> & BPCL by the Supplier for approval within 30 days from<br />

the date of Purchase Order wherever specified therein. No part shipment shall be made without<br />

approval of billing schedule.<br />

2.6.5 Subject to Technical Acceptability, For supplies sourced within India (if any) by Foreign<br />

Bidder & directly dispatched to Site shall have following provisions: (Refer Annexure-A)<br />

3.0 OCEAN FREIGHT:<br />

3.1 Ocean freight from FOB Port of Exit to designated Indian Port shall be arranged by BPCL through<br />

their nominated Freight Forwarder. Supplier shall arrange handing over the material to BPCL Freight<br />

Forwarder at the designated Port of Exit.<br />

3.2 In cases where the RFQ requires the Supplier to quote Ocean Freight, BPCL reserves the right to<br />

ask the Supplier to arrange shipment through their own Freight Forwarder at the quoted freight<br />

rates.<br />

3.3 Owner/<strong>EIL</strong> reserves the right to place the order for foreign bidder either on FOB basis or CFR basis.<br />

In case of award, initially the order shall be placed on FOB basis and Owner reserves the right to<br />

convert the same to CFR basis within 4 months, from placement of order. Therefore, the Ocean<br />

Page 25 of 291