Iride Energia-Torino: This project involves the supply of a 150 MW steam turbo-generator for Iride<br />

Energia S.p.A. in Torino, Italy. This project commenced in June 2009 and is scheduled to be completed in<br />

May 2011. The contract value of the project is €26.00 million.<br />

Sener-Argentina: This project involves the supply of a 170 MW steam turbo-generator for Sener in<br />

Argentina. This project commenced in April 2008 and is scheduled to be completed in May 2010. The<br />

contract value of the project is €23.00 million.<br />

SAE Powerlines<br />

SAE Powerlines have been engaged for several decades in the design, fabrication and erection of transmission<br />

towers and lines worldwide. It is currently a global manufacturer of switching AC/DC and DC/DC power supplies in<br />

the power ranges from 100 to 2,200 Watts, full range of magnetic components, EMI/RFI power line filters and a<br />

providers of electronic sub-assemblies. With operations in Africa, South East Europe, Middle East, Southeast Asia<br />

and Latin America, its customers can be split into two segments: (a) utilities companies, mainly consisting of state<br />

owned companies, organized by subsystem departments with their own standard technical and commercial<br />

specifications; and (b) independent power producers and developers, mainly consisting of private companies,<br />

generally set up as special purpose companies for the project working in transnational markets. In 2008, ATSL<br />

acquired a 100.00% stake for €1.38 million in SAE Powerlines. We currently hold SAE Powerlines through our<br />

subsidiary ATSL Holdings B.V., Netherlands.<br />

For the six months ended June 30, 2009, the turnover, EBITDA and profit after tax of SAE Powerlines, as certified<br />

by its board of directors, was €33.87 million, €1.33 million and €0.08 million, respectively.<br />

Some selected ongoing major projects currently undertaken by SAE Powerlines are set forth below:<br />

Oil and Gas<br />

Commission Federal de Electricidad in Mexico: This project involved the design, fabrication and erection<br />

of a 140 kilometer transmission line on a turnkey basis for Commission Federal de Electricidad in Mexico.<br />

The contract value of the project was €55.00 million. This project was completed in 2004.<br />

Nigerian Agipoil Company in Nigeria: This project involved the design, fabrication and erection of a 55<br />

kilometer transmission line on a turnkey basis including Niger River crossing for Nigerian Agipoil<br />

Company in Nigeria. The contract value of the project was €29.00 million. This project was completed in<br />

2005.<br />

Sonelgaz in Algeria: This project involved the design, fabrication and erection of a 52 kilometer<br />

transmission line on a turnkey basis in desert area for Sonelgaz in Algeria. The contract value of the project<br />

was €10.00 million. This project was completed in 2007.<br />

In addition, SAE also entered into a contract for design, fabrication and erection of a 400/220/60kV<br />

transmission line for Sonelgaz in Algeria. The contract value of this project is €22.90 million. This project<br />

commenced in July 2008 and is scheduled to be completed in April 2010.<br />

Volta River Authority in Ghana: This project involved the design, fabrication and erection of a 140<br />

kilometer transmission line and substation on a turnkey basis for Volta River Authority in Ghana. The<br />

contract value of the project was €10.00 million. This project was completed in 2007.<br />

Operatori Sistemi e Transmetimi in Albania: This project involved the design, fabrication and erection of a<br />

400 kV transmission line between Tirana and Elbasan for Operatori Sistemi e Transmetimi in Albania. The<br />

contract value of the project is €10.50 million. This project was commenced in April 2008 and is scheduled<br />

to be completed in March 2010.<br />