RISK FACTORS<br />

An investment in equity shares involves a degree of risk. You should carefully consider all the information<br />

in this Preliminary Placement Document, including the risks and uncertainties described below and the<br />

information under ―Forward-Looking Statements‖, before making an investment in the Equity Shares. If the<br />

following risks actually occur, our business, results of operations and financial condition could suffer, and<br />

the price of the Equity Shares and the value of your investment in the Equity Shares could decline. Unless<br />

specified or quantified in the risk factors below, we are not in a position to quantify the financial<br />

implications of any of the risks mentioned below. Additional risks not described below or not currently<br />

known to us or that we currently deem immaterial may also adversely affect the market price of our Equity<br />

Shares.<br />

Risks Related to Our EPC and Construction Business<br />

Our EPC and construction business is exposed to risks associated with cost overruns or underestimations<br />

in our fixed price, turnkey and item rate contracts.<br />

While a majority of our contracts contain a price escalation clause, some of our contracts are fixed-price<br />

contracts. In the case of turnkey contracts, we generally agree to deliver completed facilities which are in a<br />

ready-to-operate condition. Our contracts may lack provisions relating to adjustment as a result of change in<br />

material and labor costs. Contract prices are based on a number of assumptions underlying our bids for such<br />

contracts as well as the competition we face while bidding for the projects. If any of these estimates prove<br />

to be inaccurate, or circumstances change, cost overruns could occur and we would experience reduced<br />

profits or, in some cases, losses. In addition to any incorrect estimates as a result of incorrect internal<br />

projections, variations in the costs from those estimated by us could be caused by various factors, including:<br />

changes in economic conditions;<br />

increases in the price and availability of labor, equipment and materials;<br />

failure in the supply of materials, services and finished goods from third parties;<br />

unanticipated changes in engineering design of the project;<br />

inaccuracies of drawings and technical information on which bids were based;<br />

unforeseen design and engineering construction conditions, site and geological conditions, which<br />

may result in delays;<br />

inability to obtain requisite environmental and other approvals;<br />

delays in the delivery of equipment and materials to the project site;<br />

unanticipated increases in equipment costs;<br />

accidents at our project sites or in surrounding areas;<br />

changes in applicable taxation structure; and<br />

delays caused by local and seasonal weather conditions.<br />

Under item rate contracts, we quote rates for individual items of work based on a schedule of quantities or<br />

bill of quantity (―BOQ‖), which is furnished by our customers. The BOQ is an estimate of the quantity of<br />

activities involved and these quantities may be varied by the parties during the course of the project, without<br />

any corresponding change in consideration.<br />

These factors could adversely affect our profitability on the affected contracts, and may result in reduced<br />

profitability or losses on our projects. Depending on the size of such projects, the resulting deviation from<br />

estimated contract performance could have a significant effect on our results of operations.<br />

Our EPC and construction business requires a considerable amount of working capital as well as<br />

investment in plant and equipment and we may be unable to adequately finance such capital needs<br />

through cash generated from our operations, advances from the clients and short-term bank borrowings.<br />