23.04.2014 Views

Innovation in Global Power - Parsons Brinckerhoff

Innovation in Global Power - Parsons Brinckerhoff

Innovation in Global Power - Parsons Brinckerhoff

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Transport<strong>in</strong>g <strong>Power</strong> Across the Grid<br />

The transmission project was built along exist<strong>in</strong>g roadways and<br />

on four plots of land to accommodate the three substations and<br />

switch<strong>in</strong>g station (Figure 2). Some 18 km (11 miles) of the<br />

transmission l<strong>in</strong>e crosses paddy fields through an optimized<br />

bypass route around Banteay Meanchey to reduce the need<br />

to acquire land <strong>in</strong> the town. This section uses self-support<strong>in</strong>g<br />

steel lattice<br />

towers 35 m<br />

(115 feet) high,<br />

which allow<br />

260-m (853-foot)<br />

conductor spans,<br />

thus reduc<strong>in</strong>g the<br />

number of towers<br />

and attendant<br />

land purchases.<br />

Figure 2: Transmission towers cross<strong>in</strong>g a<br />

rice paddy field between Battambang and<br />

Banteay Meanchey.<br />

In 2005, a thirtyyear<br />

concession<br />

to develop a<br />

build, operate and transfer (BOT) project was awarded by the<br />

government of Cambodia through EDC to Cambodia <strong>Power</strong><br />

Transmission L<strong>in</strong>es (CPTL), a private jo<strong>in</strong>t venture between SKL<br />

Group’s A.S.K. Co., Ltd. and M O Consolidation Service Ltd. A<br />

power transmission agreement (PTA) was signed between EDC<br />

and CPTL committ<strong>in</strong>g EDC to pay a transmission charge<br />

calculated from the amount of 22 kV energy received at<br />

the various delivery po<strong>in</strong>ts.<br />

PB’s Involvement<br />

The transmission project is the first private sector power<br />

transmission project <strong>in</strong> Cambodia and one of the country’s<br />

first commercially f<strong>in</strong>anced projects. PB was appo<strong>in</strong>ted by<br />

Asian Development Bank (ADB) to serve as the lender’s<br />

eng<strong>in</strong>eer for ADB and a small group of commercial lenders<br />

on a US $20 million loan to CPTL. The total cost of the<br />

project was estimated at US $34 million.<br />

Our team visited the project on a number of occasions,<br />

conduct<strong>in</strong>g <strong>in</strong>spections before and dur<strong>in</strong>g construction, which<br />

commenced <strong>in</strong> January 2006, and prior to energization <strong>in</strong><br />

November 2007. In December 2007, we completed the<br />

technical due diligence by report<strong>in</strong>g on the design and<br />

<strong>in</strong>stallation of the substation and transmission l<strong>in</strong>es and on<br />

the outstand<strong>in</strong>g environmental and social issues.<br />

The project <strong>in</strong>volved the collaboration of PB specialists<br />

among different discipl<strong>in</strong>es (PB advised ADB on technical,<br />

environmental and social issues) and across different cont<strong>in</strong>ents<br />

(PB specialists were sourced from Australia, S<strong>in</strong>gapore, the<br />

Middle East, Hong Kong and Thailand).<br />

Project Challenges<br />

http://www.pbworld.com/news_events/publications/network/<br />

While the project, be<strong>in</strong>g a basic transmission l<strong>in</strong>e, was<br />

appropriately straightforward and did not present particularly<br />

difficult or <strong>in</strong>novative technology, work<strong>in</strong>g with<strong>in</strong> a country<br />

that is develop<strong>in</strong>g and is largely undeveloped outside the ma<strong>in</strong><br />

cities proved challeng<strong>in</strong>g. Issues that were <strong>in</strong>terest<strong>in</strong>g and somewhat<br />

unique to this project <strong>in</strong>cluded those discussed below.<br />

Former War Zone Challenges. The transmission l<strong>in</strong>e<br />

crossed ‘no man’s land,’ a 600-m (2,000-foot)-wide strip<br />

between Cambodia and Thailand that was heavily m<strong>in</strong>ed<br />

dur<strong>in</strong>g Cambodia’s civil war. This well-vegetated area (a result<br />

of the landm<strong>in</strong>es) is owned by neither Thailand nor Cambodia,<br />

although both countries wish to keep the land <strong>in</strong> its current<br />

state for security reasons. The presence of landm<strong>in</strong>es over<br />

this wide swath resulted <strong>in</strong> the design and construction of<br />

two suspension-type towers 82 m (269 feet) high supported<br />

by two anchor-type transmission towers 44 m (144 feet) high).<br />

This design was used previously for cross<strong>in</strong>g the Mekong River.<br />

The ground below the transmission l<strong>in</strong>e close to this border<br />

had to be cleared of landm<strong>in</strong>es before construction could beg<strong>in</strong>.<br />

Technical Challenges. We concluded that the substations and<br />

switch<strong>in</strong>g station had been <strong>in</strong>stalled and tested to a high standard<br />

and the components were determ<strong>in</strong>ed to be well proven and<br />

of standard design.<br />

As with all projects, there were local conditions to consider.<br />

Flood<strong>in</strong>g of the fields <strong>in</strong> the wet season, for example,<br />

<strong>in</strong>fluenced the materials and structural aspects of the poles.<br />

We were required to verify whether the poles were of a<br />

design suitable for the terra<strong>in</strong>. Concerns were raised follow<strong>in</strong>g<br />

two separate <strong>in</strong>cidents <strong>in</strong> which the concrete poles had<br />

failed, result<strong>in</strong>g <strong>in</strong> the collapse of the several poles. Reasons<br />

for these failures were:<br />

• A Caterpillar excavator that was work<strong>in</strong>g on a separate road<br />

upgrade project dug around one of the pole foundations<br />

and exerted pressure on the exposed foundation.<br />

• A large mango tree blew onto the l<strong>in</strong>e dur<strong>in</strong>g a heavy storm.<br />

Our assessment was that the poles had been constructed to<br />

<strong>in</strong>ternational standards, but were subjected to undue forces<br />

that they were not designed for (nor would be expected to<br />

be designed for) as a result of third party actions and<br />

extreme weight that was above the design loads.<br />

Improvements are still be<strong>in</strong>g made <strong>in</strong> order to balance the<br />

requirements of the transmission project with other development<br />

<strong>in</strong>frastructure projects <strong>in</strong> Cambodia. In one <strong>in</strong>stance a<br />

temporary road bypass scheme meant that one of the transmission<br />

poles ended up <strong>in</strong> the middle of a carriageway with<br />

cars hav<strong>in</strong>g to drive on either side of it. In another, a heavy<br />

vehicle weigh station (from another project) had been built<br />

PB Network #68 / August 2008 60

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!