Funding:<br />
Project Amount<br />
SAP Grants<br />
CPB Manager: DuBois, Stephanie Grant Amount: $130,000.00<br />
Population Served by This Project 10 Loan Amount: $0.00<br />
Project Phase:<br />
Problem:<br />
Solution:<br />
Project:<br />
Grant Agreement Phase<br />
rely on existing wells<br />
install water distribution lines to homes within the Los Padillas area<br />
waterline extension to Malpais road and streets in Los Padillas community<br />
$0.00<br />
Fund Balance: $130,000.00<br />
To design and construct improvements for the south valley water project, including extension to Malpais road and<br />
streets in Los Padillas community of the south valley of Bernalillo county. Funds will be used towards phase 7 of<br />
the S.Valley distribution system. 11-1-12 grant agreement executed. As of 12-5-12 there has been no further<br />
activity.<br />
County: Bernalillo<br />
CPB No: WTB-76<br />
Funding: WTB<br />
Bernalillo, County of<br />
Project Amount<br />
$3,900,000.00<br />
CPB Manager: DuBois, Stephanie Grant Amount: $3,900,000.00<br />
Population Served by This Project 100 Loan Amount: $0.00<br />
Project Phase:<br />
Problem:<br />
Solution:<br />
Project:<br />
Construction<br />
Lack of water to Cordero Mesa Business Park<br />
Install water transmission line<br />
Water <strong>Infrastructure</strong> Improvements<br />
Fund Balance: $3,361,224.89<br />
$3,900,000 for multiple phases for the installation of 18,000 linear feet of water transmission lines to serve the<br />
Cordero Mesa Business Park. NMFA MOU expired June 30, 2012. No activity by CPB pending new MOU.<br />
I-40 & Shelly Drive Transmission Line<br />
Phase 1_9-7-11 CPB approved plans/specs for the Cordero Mesa waterline (bid lot #2) for bid advertisement. 10-<br />
26-11 CPB approved bid tabulation awarding contract to Franklin's Earthmoving. WTB funding will only be utilized<br />
toward bid items 24-50 under bid lot #2, $363,295.60. 11-4-11 pre-construction meeting held. 1-23-12 CPB<br />
approved change order #1. 2-16-12 CPB conducted final inspection. 5-18-12 CPB approved change order #2 for<br />
final adjusting quantities. 10-31-12 all closeout documentation received.<br />
Phase 2_36-inch Transmission Line<br />
6-27-12 CPB reviewed & commented on design plans/specs for 36-inch installation of transmission line. 9-21-12<br />
CPB approved plans/specs for bid advertisement. 10-25-12 County awarded project to AUI in the amount of<br />
$3,797,978.55. 11-28-12 County held pre-construction meeting. 12-10-12 County issued notice to proceed.<br />
County: Bernalillo<br />
Bernalillo, County of<br />
CPB No: XP-00F08101<br />
Funding:<br />
Project Amount<br />
STAG<br />
CPB Manager: DuBois, Stephanie Grant Amount: $1,067,000.00<br />
Population Served by This Project 100 Loan Amount: $0.00<br />
Project Phase:<br />
Problem:<br />
Solution:<br />
Project:<br />
Planning Phase<br />
Septic tanks contaminating groundwater<br />
Remove existing septic tanks & install sewer collection lines<br />
Coors Vacuum Sewer<br />
$0.00<br />
Fund Balance: $1,067,000.00<br />
$1,067,000 FY (09) Coors Vacuum Sewer project. 9-20-07 reaffirmation of finding of no significant impact (FNSI)<br />
for South Valley became final. 2-16-11 CPB received copy of cooperative agreement and project description.10-26-<br />
11 CPB notified County the reaffirmation of the FNSI expires 10-20-2012. Project must be under construction<br />
before the expiration date. 3-7-12 CPB received request for second reaffirmation of finding of no significant impact<br />
(FNSI) for Valley Utilities projects. 4-16-12 public hearing held. 5-10-12 CPB emailed documentation to EPA to<br />
process 2nd reaffirmation of FNSI. 10-15-12 EPA denied request for 2nd FNSI reaffirmation. As of 12-17-12<br />
County is completing NEPA process to have EPA issue a new FNSI for project.