County: Sandoval<br />
Algodones MDWCA<br />
CPB No: 2460-PG<br />
Funding:<br />
Project Amount<br />
NMFA-PG<br />
$37,500.00<br />
CPB Manager: DuBois, Stephanie Grant Amount: $37,500.00<br />
Population Served by This Project 675 Loan Amount: $0.00<br />
Project Phase:<br />
Problem:<br />
Solution:<br />
Project:<br />
Planning Phase<br />
Fund Balance: $37,500.00<br />
Not meeting the Drinking water arsenic standard.<br />
Funding is to develop preliminary engineering report to outline alternatives for treatment.<br />
PER for Arsenic Treatment<br />
$50,000 complete preliminary engineering report (PER). 11-10-11 CPB reviewed and commented on request for<br />
proposals (RFP) to hire an engineering firm. 12-7-11 CPB commented on award to Souder Miller since only 1-<br />
proposal was received. 3-7-12 CPB approved draft engineering contract for execution. As of 4-26-12 SMA is<br />
gathering as-built data from Sandoval County. As of 9-12-12 Planning grant contract with NMFA has not been<br />
renewed. 11-13-12 CPB commented on preliminary engineering report.<br />
County: Sandoval<br />
Algodones MDWCA<br />
CPB No: SAP 12-1631-STB<br />
Funding:<br />
Project Amount<br />
SAP Grants<br />
CPB Manager: DuBois, Stephanie Grant Amount: $66,464.61<br />
Population Served by This Project 675 Loan Amount: $0.00<br />
Project Phase:<br />
Problem:<br />
Solution:<br />
Project:<br />
Grant Agreement Phase<br />
system does not meet Drinking water standards for arsenic<br />
develop preliminary engineering report to outline alternatives for arsenic treatment<br />
water system improvements to reduce arsenic levels<br />
$0.00<br />
Fund Balance: $66,464.61<br />
$66,464.61 to plan and design water system improvements to reduce arsenic levels for the Algodones mutual<br />
domestic water consumers and mutual sewage works association in Sandoval county. 11-13-12 CPB commented<br />
on preliminary engineering report. Grant agreement has not been executed.<br />
County: Sandoval<br />
Bernalillo, Town of<br />
CPB No: XP-966855<br />
Funding:<br />
Project Amount<br />
STAG<br />
$477,000.00<br />
CPB Manager: DuBois, Stephanie Grant Amount: $477,000.00<br />
Population Served by This Project 9,200 Loan Amount: $0.00<br />
Project Phase:<br />
Problem:<br />
Solution:<br />
Project:<br />
Construction<br />
tanks interior & exterior paint is wearing off<br />
Rehab interior & exterior of tanks 1 & 2<br />
rehab tanks 1 & 2<br />
Fund Balance: $477,000.00<br />
$477,000 Town of Bernalillo rehab of tanks 1 & 2. 11-4-09 EPA issued CE. 2-18-11 CPB received executed<br />
engineering agreement with Smith Engineering. 12-6-11 EPA emailed that original CE is valid for well sites 3 &4 and<br />
tank rehabs. 1-26-12 CPB approved plans/specs for bid advertisement. 4-16-12 EPA approved time extension to<br />
12-30-12. 5-29-12 CPB approved bid tabulation awarding construction contract to D&R Tank. 6-25-12 CPB<br />
attended pre-construction meeting. 8-28-12 site inspection conducted. As of 12-13-12 construction is 100%<br />
complete. Waiting for final closeout documentation.<br />
46