County: Rio Arriba<br />
Chama, Village of<br />
CPB No: CWSRF 013G<br />
Funding:<br />
Project Amount<br />
CWSRF<br />
$850,000.00<br />
CPB Manager: Telmo, Andrea Loan Amount: $0.00<br />
Population Served by This Project 1,200 Grant Amount: $850,000.00<br />
Project Phase: Planning Phase Fund Balance: $850,000.00<br />
Problem:<br />
Solution:<br />
Project:<br />
The existing WWTP has been unable to consistently meet requirements set forth in the Village's<br />
National Pollution Discharge Elimination System (NPDES) Permit. The plant has numerous<br />
operational violations and has received 2 Administrative Orders from EPA.<br />
Plan, design and construct a new WWTP that will be in compliance with the NPDES permit.<br />
Plan & Design new WWTP<br />
Village has advertised RFP for engineering services for design of new WWTP. Proposals are due December 21,<br />
2012.<br />
County: Rio Arriba<br />
Chamita MDWCA & SWA<br />
CPB No: RIP 2012-07<br />
Funding:<br />
Project Amount<br />
RIP Loans<br />
$319,000.00<br />
CPB Manager: Telmo, Andrea Grant Amount: $0.00<br />
Population Served by This Project 1,200 Loan Amount: $319,000.00<br />
Project Phase:<br />
Problem:<br />
Solution:<br />
Project:<br />
Ad/Bid Phase<br />
Fund Balance: $319,000.00<br />
No backup water supply.<br />
Drill new well as backup water supply. Construct pump house and connect new well to distribution<br />
system.<br />
water well and pump house<br />
RIP loan funding will supplement SAP 12-1362-STB. Plans and specs approved by CPB August 2011. Engineering<br />
contract for bidding and construction phase services approved by CPB November 2012.<br />
County: Rio Arriba<br />
Chamita MDWCA & SWA<br />
CPB No: SAP 12-1362-STB<br />
Funding:<br />
Project Amount<br />
SAP Grants<br />
CPB Manager: Telmo, Andrea Grant Amount: $75,000.00<br />
Population Served by This Project 1,200 Loan Amount: $0.00<br />
Project Phase:<br />
Problem:<br />
Solution:<br />
Project:<br />
Ad/Bid Phase<br />
lack of water<br />
drill new well<br />
supplemental well<br />
$0.00<br />
Fund Balance: $75,000.00<br />
$75,000 to plan, design, drill, construct and equip a supplemental well for the Chamita mutual domestic water<br />
consumers and sewage works association in Rio Arriba county. RIP loan 2012-07 will supplement SAP funding.<br />
Plans and specs approved by CPB August 2011. CPB approved engineering contract for bidding and construction<br />
phase services November 2012.<br />
County: Rio Arriba<br />
Espanola, City of<br />
CPB No: WTB-110<br />
Funding:<br />
Project Amount<br />
WTB<br />
$2,580,000.00<br />
CPB Manager: Telmo, Andrea Grant Amount: $2,580,000.00<br />
Population Served by This Project 10,224 Loan Amount: $0.00<br />
Project Phase: Ad/Bid Phase Fund Balance: $2,106,327.18<br />
Problem:<br />
Solution:<br />
Project:<br />
Well No. 4 is contaminated with arsenic and fluoride and Well No. 7 is contaminated with nitrate.<br />
Construct waterline and tank to allow for blending of water from Wells No. 4 and No. 7 in Tank<br />
No. 4 to reduce contaminant concentrations below MCLs.<br />
San Juan Diversion Project<br />
Funding will be used for the Well No. 4 & Well No. 7 Blending Project and Tank No. 4 Replacement Project. NMFA<br />
MOU expired June 30, 2012. No activity by CPB pending new MOU.<br />
36