County: McKinley<br />
Gallup, City of<br />
CPB No: WTB-111<br />
Funding:<br />
Project Amount<br />
WTB<br />
$5,883,865.00<br />
CPB Manager: Bishop, David Grant Amount: $5,883,865.00<br />
Population Served by This Project 21,678 Loan Amount: $0.00<br />
Project Phase: Grant Agreement Phase Fund Balance: $5,702,063.80<br />
Problem:<br />
Solution:<br />
Project:<br />
Several individual water systems need upgrades and repairs to systems but lack recourses for<br />
improvements.<br />
Regionalize systems.<br />
Storage Conveyance and Delivery<br />
Planning and design of Navajo Gallup Water Supply Project, specifically for Water Supply Project 3 and Project 4.<br />
Project 3: Installation of 10,000 lf of 12" DIP and 7,000 lf of 24" DIP. Project 4: waterline to connect to Twin Lakes<br />
well, 300,000 gal tank at Tolakia and 500,000 gal tank at Yah Ta hey Pump Station. Project 3 is complete with<br />
Substantial Completion on 4/4/11 and Final Inspection on 4/28/11. Some pay requests are currently being<br />
submitted. Balance will be used towards Navajo Gallup Water Supply Projects 4 and 7-13. These projects are<br />
currently waiting for approval of funding programmatic agreement. P&S for Projects 4, 5 and 6 expect to be<br />
completed by June 2012. 6/6/12 Projects 4, 5 & 6 in design. 12/6/12 NMFA MOU expired June 30, 2012. No<br />
activity by CPB pending new MOU. 12/10/12 NMFA MOU expired June 30, 2012. No activity by CPB pending new<br />
MOU.<br />
County: McKinley<br />
Gallup, City of<br />
CPB No: WTB-150<br />
Funding:<br />
Project Amount<br />
WTB<br />
$1,601,856.00<br />
CPB Manager: Bishop, David Grant Amount: $1,601,856.00<br />
Population Served by This Project 21,678 Loan Amount: $0.00<br />
Project Phase: Grant Agreement Phase Fund Balance: $1,049,871.25<br />
Problem:<br />
Solution:<br />
Project:<br />
Several individual water systems need upgrades and repairs to systems but lack recourses for<br />
improvements.<br />
Regionalize systems.<br />
Water Storage, Conveyance and Delivery<br />
Planning and design of Navajo Gallup Water Supply Project, specifically for Water Supply Project 5 and Project 6.<br />
Project 5: Gamerco Tank 3.0 MG and piping, Project 6: 18" ductile iron pipe east side water line. Projects are<br />
currently in planning and design. 12/12/11 Geotechnical & Cultural services currently taking place. P&S about 30%<br />
complete and should be completed by about June 2012. 6/6/12 Navajo Gallup Water Supply Projects 5 & 6 are<br />
currently waiting for approval of funding programmatic agreement. 12/10/12 NMFA MOU expired June 30, 2012. No<br />
activity by CPB pending new MOU.<br />
County: McKinley<br />
McKinley, County of<br />
CPB No: WTB-198<br />
Funding:<br />
Project Amount<br />
WTB<br />
$1,859,703.00<br />
CPB Manager: Bishop, David Grant Amount: $1,859,703.00<br />
Population Served by This Project 1,500 Loan Amount: $0.00<br />
Project Phase: Grant Agreement Phase Fund Balance: $1,395,273.37<br />
Problem:<br />
Solution:<br />
Project:<br />
Numerous individual water systems require inordinate amount of assistance by City of Gallup.<br />
Regionalize systems.<br />
Water Storage, Conveyance and Delivery<br />
Project consists of planning, design and construction of infrastructure improvement projects included in Phase II of<br />
McKinley Co Small Systems Regionalization Plan. These include projects for four water associations (Yah Ta Hey<br />
WSD, White Cliffs MDWUA, Gamerco WSD and Coal Basin MDWUA). 1/4/12 CPB reviews and approves revised<br />
P&S. 2/15/12 CPB reviews bid tabs and concurs with award to Dallago Corporation for the Small System<br />
Regionalization Phase 2A prj in the amount of $877,805.25 12/10/12 NMFA MOU expired June 30, 2012. No<br />
activity by CPB pending new MOU.<br />
25