County: Sandoval<br />

Corrales, Village of<br />

CPB No: CWSRF-011G<br />

Funding:<br />

Project Amount<br />

CWSRF<br />

$1,000,000.00<br />

CPB Manager: DuBois, Stephanie Loan Amount: $0.00<br />

Population Served by This Project 80 Grant Amount: $1,000,000.00<br />

Project Phase: Construction Fund Balance: $595,455.51<br />

Problem:<br />

Solution:<br />

Project:<br />

Corrales has no existing sewer system & rely on old leaking septic tanks<br />

install sewer collection system for business core area<br />

Corrales Sewer System<br />

$1,540,000 for design and construction of sewer system improvements. 7-20-11 CPB approved phase 3<br />

preliminary engineering report (PER) amendment. 10-12-11 CPB approved phase 3 environmental information<br />

document (EID) amendment. 9-27-11 CPB reviewed plans/specs. 10-25-11 CPB sent environmental assessment<br />

(EA)/finding of no significant impact (FNSI) to Corrales for advertisement & submittal to agencies. 12-24-11<br />

Corrales advertised FNSI for 30-day comment period. 1-25-12 final determination issued for FNSI. 1-26-12 CPB<br />

approved plans/specs. 2-22-12 CPB approved bid tabulation awarding construction contract to K.R. Swerdfeger<br />

Construction, Inc. in the amount of $957,800 (excludes tax). 2-23-12 CPB attended pre-construction meeting. 4-16-<br />

12 CPB conducted site inspection. 9-4-12 attended final walk through inspection. As of 11-19-12 contractor<br />

completed punch list items and is working on final closeout documentation.<br />

County: Sandoval<br />

Cuba, Village of<br />

CPB No: SAP 09-3809-STB<br />

Funding:<br />

Project Amount<br />

SAP Grants<br />

CPB Manager: Bishop, David Grant Amount: $100,000.00<br />

Population Served by This Project 731 Loan Amount: $0.00<br />

Project Phase: Construction Fund Balance: $100,000.00<br />

Problem:<br />

Solution:<br />

Project:<br />

Existing wastewater treatment plant does not meet NPDES permit requirements.<br />

Upgrade wastewater treatment plant so effluent will meet NPDES permit requirements.<br />

Wastewater System and Facility Improvements<br />

to plan, design, construct and improve the wastewater treatment system in Cuba in Sandoval county. 1/23/12 CPB<br />

issues FONSI and Final Determination Letter. 2/29/12 CPB reviews and approves Revised Plans & Specs to<br />

advertise for bids. Bids were advertised 2/12/12, prebid conference will be on 2/28/12 and bids will be opened on<br />

3/13/12. 6/5/12 Low bidder is TLC; Given NTP on 4/30/12. 12/10/12 Construction is 56% complete; Gannett<br />

Fleming is 30% complete on PER for Phase 2<br />

County: Sandoval<br />

Cuba, Village of<br />

CPB No: SAP 09-3810-STB<br />

Funding:<br />

Project Amount<br />

SAP Grants<br />

CPB Manager: Bishop, David Grant Amount: $350,000.00<br />

Population Served by This Project 731 Loan Amount: $0.00<br />

Project Phase: Construction Fund Balance: $123,725.01<br />

Problem:<br />

Solution:<br />

Project:<br />

Existing wastewater treatment plant does not meet NPDES permit requirements.<br />

Upgrade wastewater treatment plant so effluent will meet NPDES permit requirements.<br />

Wastewater Treatment System Improvements<br />

to plan, design, construct and improve the wastewater treatment system in Cuba in Sandoval county. 1/23/12 CPB<br />

issues FONSI and Final Determination Letter. 2/29/12 CPB reviews and approves Revised Plans & Specs to<br />

advertise for bids. Bids were advertised 2/12/12, prebid conference will be on 2/28/12 and bids will be opened on<br />

3/13/12. 6/5/12 Low bidder is TLC; Given NTP on 4/30/12. 12/10/12 Construction is 56% complete; Gannett<br />

Fleming is 30% complete on PER for Phase 2<br />

$0.00<br />

$0.00<br />

47