County: Dona Ana<br />

Anthony Water and Sanitation District<br />

CPB No: WTB-75<br />

Funding:<br />

Project Amount<br />

WTB<br />

$500,000.00<br />

CPB Manager: Deal, Steven Grant Amount: $500,000.00<br />

Population Served by This Project 9,360 Loan Amount: $0.00<br />

Project Phase: Construction Fund Balance: $500,000.00<br />

Problem:<br />

Solution:<br />

Project:<br />

Certain wells in the Anthony Water and Sanitation District are contaminated with nitrates and<br />

arsenic.<br />

A reverse osmosis system has been designed to remove the contaminants.<br />

Phase III Rehabilitation Project<br />

Project had a bid opening on December 29, 2011. Bid information has not been provided as of January 4, 2012.<br />

SD Project is in construction. SD 7/9/12<br />

NMFA MOU expired June 30, 2012. No activity by CPB pending new MOU. 12/20/12 SD<br />

County: Dona Ana<br />

Desert Aire MDW&SA<br />

CPB No: 2488-PG<br />

Funding:<br />

Project Amount<br />

NMFA-PG<br />

$50,000.00<br />

CPB Manager: Deal, Steven Grant Amount: $50,000.00<br />

Population Served by This Project 736 Loan Amount: $0.00<br />

Project Phase: Planning Phase Fund Balance: $50,000.00<br />

Problem: The Association is concerned about protecting groundwater and potentially allowing empty lots<br />

smaller than 0.75 acres to be developed.<br />

Solution: A Preliminary Engineering <strong>Report</strong> (PER) and <strong>Environment</strong>al Information Document (EID) have<br />

been developed to examine specific engineering solutions to wastewater collection and treatment<br />

outside of septic systems.<br />

Project: PER for Wastewater Improvements<br />

Comments have been made and returned to the Association and the consulting engineer for the PER (9/27/11)<br />

and the EID/EA (10/4/11). No revisions or response to comments have been provided by 1/5/12. SD Preliminary<br />

Engineering <strong>Report</strong> (PER) update is being reviewed. But, new information about Doña Ana County's intentions in<br />

the area has come to light that may impact the PER update scope. SD 12/11/12<br />

County: Dona Ana<br />

Dona Ana County<br />

CPB No: SAP 11-1296-STB<br />

Funding:<br />

Project Amount<br />

SAP Grants<br />

CPB Manager: Deal, Steven Grant Amount: $1,250,000.00<br />

Population Served by This Project 12,000 Loan Amount: $0.00<br />

Project Phase: Planning Phase Fund Balance: $1,250,000.00<br />

Problem: Upgrading waterlines and other water infrastructure in the Camino Real Regional Utility Authority<br />

(CRRUA) service area.<br />

Solution: Multiple projects are being contemplated to design a new well and tank for the City of Sunland<br />

Park.<br />

Project: To plan, design, construct improvements to the water supply and distribution system,<br />

including replacing wells and fire pumps, serving Santa Teresa and surrounding areas in<br />

Doña Ana County<br />

Notice of Obligation submitted for two contracts totaling $225,727.20 including NMGRT of 7%. SD 04/05/12; have<br />

added a distribution change order from the Santa Teresa industrial park arsenic project for $221,477.36. SD<br />

9/26/12 Total obligated amount is for $447,204.56 with projects ongoing. No disbursement requests have been<br />

submitted to date. SD 12/11/12<br />

$0.00<br />